Assessment Year | 2000 |
---|---|
Principal Product | Amino Acids |
NAICS |
n/a
|
SIC | 2833: Medicinal Chemicals and Botanical Products |
Sales Range | $10 M to 50M |
# of Employees | 50 |
Plant Area |
65,340
ft2
|
Annual Production | 0
lb
|
Production Hrs. Annual | 1,560
hrs
|
Location (State) | Oregon |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $9,509 | 267,000 |
kWh
|
$0.036 |
Electricity Demand | $950 | 300 |
kW-mo/yr
|
$3.17 |
Electricity Fees | $950 | - |
|
- |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $264,696 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $15,477 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Other Liquid (non-haz) Savings | Personnel Changes Savings | Administrative Changes Savings | Primary Raw Material Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.6212: Turn off equipment during breaks, reduce operating time | $9,100 | - | - | - | - | - | - | - | $9,100 | - | |
02 | 2.7133: Use separate switches on perimeter lighting which may be turned off when natural light is available | $262 | - |
$181
5,275
kWh
|
- | - | - | $25 | - | - | $56 | |
03 | 2.6212: Turn off equipment during breaks, reduce operating time | $2,186 | $630 |
$2,186
63,600
kWh
|
- | - | - | - | - | - | - | |
04 | 2.4133: Use most efficient type of electric motors | $6,115 | $11,205 |
$5,165
150,350
kWh
|
$950
-
kW-mo/yr
|
- | - | - | - | - | - | |
05 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $2,083 | $6,300 |
$2,083
50,700
kWh
|
- | - | - | - | - | - | - | |
06 | 2.3212: Optimize plant power factor | $950 | $2,700 | - | - | $950 | - | - | - | - | - | |
07 | 3.8142: Distill contaminated solvents for reuse | $244,000 | $110,000 | - | - | - |
$39,310
-
gal
|
- | $(-22,900.0) | - | $227,590 | |
TOTAL RECOMMENDED | $264,696 | $130,835 |
$9,615
269,925
kWh
|
$950
-
kW-mo/yr
|
$950 |
$39,310
-
gal
|
$25 | $(-22,900.0) | $9,100 | $227,646 | ||
TOTAL IMPLEMENTED | $15,477 | $11,205 |
$5,346
155,625
kWh
|
$950
-
kW-mo/yr
|
- | - | $25 | - | $9,100 | $56 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Other Liquid (non-haz) Savings | Personnel Changes Savings | Administrative Changes Savings | Primary Raw Material Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs