| Assessment Year | 2003 |
|---|---|
| Principal Product | Electrical outlets and switches |
| NAICS |
n/a
|
| SIC | 3643: Current-Carrying Wiring Devices |
| Sales Range | $50 M to 100M |
| # of Employees | 300 |
| Plant Area |
155,000
ft2
|
| Annual Production | 100,000,000
pieces
|
| Production Hrs. Annual | 8,400
hrs
|
| Location (State) | North Carolina |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $364,509 | 12,647,100 |
kWh
|
$0.029 |
| Electricity Demand | $247,432 | 26,407 |
kW-mo/yr
|
$9.37 |
| Electricity Fees | $19,107 | - |
|
- |
| Natural Gas | $27,612 | 4,031 |
MMBtu
|
$6.85 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $33,092 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $18,311 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Water Disposal Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.4239: Eliminate or reduce compressed air usage | $14,411 | $20,000 |
$8,714
302,578
kWh
|
$5,697
-
kW-mo/yr
|
- | |
| 02 | 2.7241: Install outside air damper / economizer on hvac unit | $10,800 | $6,000 |
$10,800
374,990
kWh
|
- | - | |
| 03 | 2.7111: Reduce illumination to minimum necessary levels | $240 | $100 |
$145
5,040
kWh
|
$95
-
kW-mo/yr
|
- | |
| 04 | 2.2625: Chill water to the highest temperature possible | $1,917 | $400 |
$1,306
45,360
kWh
|
$611
-
kW-mo/yr
|
- | |
| 05 | 2.5194: Redesign process | $4,814 | $780 |
$3,281
113,935
kWh
|
$1,533
-
kW-mo/yr
|
- | |
| 06 | 2.7228: Avoid introducing hot, humid, or dirty air into hvac system | $780 | $1,000 |
$384
13,345
kWh
|
$396
-
kW-mo/yr
|
- | |
| 07 | 3.4116: Meter recycled water (to reduce sewer charges) | $130 | $350 | - | - |
$130
-
Tgal
|
|
| TOTAL RECOMMENDED | $33,092 | $28,630 |
$24,630
855,248
kWh
|
$8,332
-
kW-mo/yr
|
$130
-
Tgal
|
||
| TOTAL IMPLEMENTED | $18,311 | $8,180 |
$15,771
547,630
kWh
|
$2,540
-
kW-mo/yr
|
- | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Water Disposal Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs