ITAC Assessment: OR0371
ITAC logo
ITAC Assessment: OR0371
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2000
Principal Product Frozen Onions
NAICS
n/a
SIC 2037: Frozen Fruits, Fruit Juices, and Vegetables
Sales Range $5
M
to 10
M
# of Employees 40
Plant Area 40,000
ft2
Annual Production 30,100,000
lb
Production Hrs. Annual 6,744
hrs
Location (State) Oregon

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $119,403 5,007,913
kWh
Electricity Demand $31,583 120,060
kW-mo/yr
Natural Gas $59,771 11,103
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $188,175 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $19,823

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Other Energy Savings Personnel Changes Savings Primary Raw Material Savings Water Consumption Savings
01 2.3212: Optimize plant power factor $3,523 $6,600 - - $3,523 - - - - -
02 2.3413: Burn fossil fuel to produce steam to drive a steam turbine-generator and use steam exhaust for heat $16,300 $20,000 - - - $37,500
-
MMBtu
$(-21,700.0)
-
MMBtu
- - $500
-
Tgal
03 4.441: Install automatic packing equipment $142,687 $81,200 $(-1,525.0)
(-61,841)
kWh
$(-508.0)
-
kW-mo/yr
- - - $144,720 - -
04 3.2176: Increase use of automation $25,665 $2,234 $(-185.0)
(-7,620)
kWh
$(-150.0)
-
kW-mo/yr
- - - - $26,000 -
TOTAL RECOMMENDED $188,175 $110,034 $(-1,710.0)
(-69,461)
kWh
$(-658.0)
-
kW-mo/yr
$3,523 $37,500
-
MMBtu
$(-21,700.0)
-
MMBtu
$144,720 $26,000 $500
-
Tgal
TOTAL IMPLEMENTED $19,823 $26,600 - - $3,523 $37,500
-
MMBtu
$(-21,700.0)
-
MMBtu
- - $500
-
Tgal
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs