Assessment Year | 2000 |
---|---|
Principal Product | Manufactured Homes |
NAICS |
n/a
|
SIC | 2451: Mobile Homes |
Sales Range | $10 M to 50M |
# of Employees | 208 |
Plant Area |
n/a
|
Annual Production | 1,664
pieces
|
Production Hrs. Annual | 0
hrs
|
Location (State) | Oregon |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $69,773 | 1,848,769 |
kWh
|
$0.038 |
Electricity Demand | $21,510 | 66,732 |
kW-mo/yr
|
$0.32 |
Electricity Fees | $252 | - |
|
- |
Natural Gas | $75,096 | 12,137 |
MMBtu
|
$6.19 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $135,390 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $131,301 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings | Primary Raw Material Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.2211: Use optimum temperature | $27,300 | - | - | - |
$27,300
-
MMBtu
|
- | - | - | |
02 | 2.2211: Use optimum temperature | $4,900 | $650 | - | - |
$4,900
-
MMBtu
|
- | - | - | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,673 | $2,050 |
$2,642
74,736
kWh
|
$1,031
-
kW-mo/yr
|
- | - | - | - | |
04 | 2.2437: Recover waste heat from equipment | $2,748 | $1,909 | - | - |
$2,748
-
MMBtu
|
- | - | - | |
05 | 4.131: Modify process to reduce material use/cost | $92,680 | - | - | - | - |
$17,000
-
lb
|
- | $75,680 | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,089 | $12,821 |
$2,155
60,961
kWh
|
$1,596
-
kW-mo/yr
|
- | - | $31 | $307 | |
TOTAL RECOMMENDED | $135,390 | $17,430 |
$4,797
135,697
kWh
|
$2,627
-
kW-mo/yr
|
$34,948
-
MMBtu
|
$17,000
-
lb
|
$31 | $75,987 | ||
TOTAL IMPLEMENTED | $131,301 | $4,609 |
$2,642
74,736
kWh
|
$1,031
-
kW-mo/yr
|
$34,948
-
MMBtu
|
$17,000
-
lb
|
- | $75,680 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings | Primary Raw Material Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs