ITAC Assessment: OR0369
ITAC logo
ITAC Assessment: OR0369
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2000
Principal Product Specialized Lumber
NAICS
n/a
SIC 2421: Sawmills and Planing Mills, General
Sales Range $1
M
to 5
M
# of Employees 23
Plant Area
n/a
Annual Production 4,800
thousand feet
Production Hrs. Annual 2,210
hrs
Location (State) Idaho

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $49,578 1,199,590
kWh
Electricity Demand $23,588 87,216
kW-mo/yr
Electricity Fees $918 -
Natural Gas $29,457 7,492
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $3,704 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $610

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Personnel Changes Savings Primary Raw Material Savings
01 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $1,963 $8,640 $1,963
47,479
kWh
- - - -
02 2.7124: Make a practice of turning off lights when not needed $199 - $100
2,345
kWh
$36
-
kW-mo/yr
- $35 $28
03 2.4111: Utilize energy-efficient belts and other improved mechanisms $200 $850 $200
4,982
kWh
- - - -
04 2.4133: Use most efficient type of electric motors $610 $4,000 $490
12,016
kWh
$120
-
kW-mo/yr
- - -
05 2.3212: Optimize plant power factor $732 $5,000 - - $732 - -
TOTAL RECOMMENDED $3,704 $18,490 $2,753
66,822
kWh
$156
-
kW-mo/yr
$732 $35 $28
TOTAL IMPLEMENTED $610 $4,000 $490
12,016
kWh
$120
-
kW-mo/yr
- - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs