Assessment Year | 2000 |
---|---|
Principal Product | Wood pellets, cat litter |
NAICS |
n/a
|
SIC | 2499: Wood Products, Not Elsewhere Classified |
Sales Range | $1 M to 5M |
# of Employees | 20 |
Plant Area |
n/a
|
Annual Production | 28,073
ton
|
Production Hrs. Annual | 4,896
hrs
|
Location (State) | Idaho |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $128,063 | 3,097,800 |
kWh
|
$0.041 |
Electricity Demand | $23,743 | 99,024 |
kW-mo/yr
|
$0.24 |
Natural Gas | $211,258 | 57,644 |
MMBtu
|
$3.66 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $78,945 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $15,000 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Primary Product Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.4322: Use or replace with energy efficient substitutes | $18,890 | $30,000 |
$16,250
393,100
kWh
|
$2,640
-
kW-mo/yr
|
- | - | - | - | |
02 | 2.2314: Replace heat treating oven with more efficient unit | $43,540 | $401,460 | - | - |
$44,000
-
MMBtu
|
- | $(-460.0) | - | |
03 | 2.4323: Use optimum size and capacity equipment | $10,000 | $4,040 | - | - | - | - | $10,000 | - | |
04 | 4.451: Add additional production shift | $5,000 | - | - | - | - | - | - | $5,000 | |
05 | 3.5212: Regrind, reuse, or sell scrap plastic parts | $1,515 | $1,500 | - | - | - |
$1,515
-
lb
|
- | - | |
TOTAL RECOMMENDED | $78,945 | $437,000 |
$16,250
393,100
kWh
|
$2,640
-
kW-mo/yr
|
$44,000
-
MMBtu
|
$1,515
-
lb
|
$9,540 | $5,000 | ||
TOTAL IMPLEMENTED | $15,000 | $4,040 | - | - | - | - | $10,000 | $5,000 |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs