ITAC Assessment: OR0363
ITAC logo
ITAC Assessment: OR0363
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2000
Principal Product adhesives, chemicals, resin
NAICS
n/a
SIC 2821: Plastics Materials, Synthetic Resins, and Nonvulcanizable Elastomers
Sales Range $10
M
to 50
M
# of Employees 16
Plant Area 1,182
ft2
Annual Production 28,000,000
lb
Production Hrs. Annual 8,760
hrs
Location (State) Oregon

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $170,651 3,554,514
kWh
Natural Gas $57,263 38,357
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $34,020 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Personnel Changes Savings Ancillary Material Cost Savings
01 4.111: Add equipment/ operators to reduce production bottleneck $15,630 $60,000 $(-750.0)
(-18,757)
kWh
$16,380 -
02 4.111: Add equipment/ operators to reduce production bottleneck $14,790 $8,100 - $14,790 -
03 4.112: Replace old machine with new automatic multi-station tool $3,600 $11,610 - $2,180 $1,420
TOTAL RECOMMENDED $34,020 $79,710 $(-750.0)
(-18,757)
kWh
$33,350 $1,420
TOTAL IMPLEMENTED - - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs