ITAC Assessment: OR0358
ITAC logo
ITAC Assessment: OR0358
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1999
Principal Product Surimi, Shrimp, Crab
NAICS
n/a
SIC 2092: Prepared Fresh or Frozen Fish and Seafoods
Sales Range $1
M
to 5
M
# of Employees 50
Plant Area 40,000
ft2
Annual Production 4,800,000
lb
Production Hrs. Annual 5,400
hrs
Location (State) Oregon

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $67,830 1,995,604
kWh
Electricity Demand $16,551 68,964
kW-mo/yr
Electricity Fees $1,461 -
Natural Gas $10,605 1,854
MMBtu
LPG $1,812 203
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $13,339 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $9,905

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Personnel Changes Savings
01 2.3212: Optimize plant power factor - $3,600 - - -
02 2.2611: Moderate cooling tower outlet temperature $2,574 $12,750 $2,574
75,615
kWh
- -
03 2.2622: Replace existing chiller with high efficiency model $860 $17,000 $860
25,205
kWh
- -
04 3.1181: Eliminate a by-product $9,905 $2,000 $1,380
40,739
kWh
$125
-
kW-mo/yr
$8,400
TOTAL RECOMMENDED $13,339 $35,350 $4,814
141,559
kWh
$125
-
kW-mo/yr
$8,400
TOTAL IMPLEMENTED $9,905 $2,000 $1,380
40,739
kWh
$125
-
kW-mo/yr
$8,400
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs