ITAC Assessment: AM0852
ITAC logo
ITAC Assessment: AM0852
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2022
Principal Product concrete strand wire
NAICS 332618: Other Fabricated Wire Product Manufacturing
SIC 3496: Miscellaneous Fabricated Wire Products
Sales Range $50
M
to 100
M
# of Employees 40
Plant Area 110,900
ft2
Annual Production 27,000
ton
Production Hrs. Annual 8,520
hrs
Location (State) Texas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $408,053 11,158,000
kWh
Electricity Demand $291,981 26,157
kW-mo/yr
Electricity Fees $73,024 -
Natural Gas $97,447 15,886
MMBtu
TOTAL YEARLY COSTS $870,505
RECOMMENDED SAVINGS* $73,754 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $59,940

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.3212: Optimize plant power factor $49,000 $68,400 - $49,000
-
kW-mo/yr
-
02 2.1233: Analyze flue gas for proper air/fuel ratio $5,040 $1,835 - - $5,040
-
MMBtu
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $5,480 $1,500 $3,850
103,980
kWh
$1,630
-
kW-mo/yr
-
04 2.7135: Install occupancy sensors $220 $385 $220
5,914
kWh
- -
05 2.2511: Insulate bare equipment $420 $235 - - $420
-
MMBtu
06 2.4111: Utilize energy-efficient belts and other improved mechanisms $6,265 - $3,385
91,490
kWh
$2,880
-
kW-mo/yr
-
07 2.7134: Use photocell controls $89 $91 $49
1,315
kWh
$40
-
kW-mo/yr
-
08 2.4231: Reduce the pressure of compressed air to the minimum required $3,170 $35 $2,230
60,196
kWh
$940
-
kW-mo/yr
-
09 2.4314: Use synthetic lubricant $4,070 $540 $2,200
59,525
kWh
$1,870
-
kW-mo/yr
-
TOTAL RECOMMENDED $73,754 $73,021 $11,934
322,420
kWh
$56,360
-
kW-mo/yr
$5,460
-
MMBtu
TOTAL IMPLEMENTED $59,940 $71,970 $3,850
103,980
kWh
$50,630
-
kW-mo/yr
$5,460
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs