ITAC Assessment: OR0357
ITAC logo
ITAC Assessment: OR0357
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1999
Principal Product Surimi,Fish,Shrimp,Crab
NAICS
n/a
SIC 2092: Prepared Fresh or Frozen Fish and Seafoods
Sales Range $10
M
to 50
M
# of Employees 200
Plant Area 40,000
ft2
Annual Production 16,790,000
lb
Production Hrs. Annual 3,600
hrs
Location (State) Oregon

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $149,501 4,359,320
kWh
Electricity Demand $31,907 113,280
kW-mo/yr
Electricity Fees $5,027 -
Natural Gas $24,647 4,924
MMBtu
LPG $7,218 512
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $724,041 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $8,771

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Personnel Changes Savings Primary Raw Material Savings Ancillary Material Cost Savings
01 4.441: Install automatic packing equipment $423,000 $140,000 - - - $437,000 - $(-14,000.0)
02 4.441: Install automatic packing equipment $91,000 $95,000 - - - $101,000 - $(-10,000.0)
03 4.441: Install automatic packing equipment $2,800 $7,000 - - - $2,800 - -
04 2.2628: Utilize a less expensive cooling method $198,470 $500,000 $(-17,140.0)
(-504,103)
kWh
$(-4,680.0)
-
kW-mo/yr
- - $210,870 $9,420
05 2.2621: Modify refrigeration system to operate at a lower pressure $7,150 - $7,150
210,434
kWh
- - - - -
06 2.3212: Optimize plant power factor $1,621 $4,800 - - $1,621 - - -
TOTAL RECOMMENDED $724,041 $746,800 $(-9,990.0)
(-293,669)
kWh
$(-4,680.0)
-
kW-mo/yr
$1,621 $540,800 $210,870 $(-14,580.0)
TOTAL IMPLEMENTED $8,771 $4,800 $7,150
210,434
kWh
- $1,621 - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Personnel Changes Savings Primary Raw Material Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs