Assessment Year | 1999 |
---|---|
Principal Product | Surimi,Fish,Shrimp,Crab |
NAICS |
n/a
|
SIC | 2092: Prepared Fresh or Frozen Fish and Seafoods |
Sales Range | $10 M to 50M |
# of Employees | 200 |
Plant Area |
40,000
ft2
|
Annual Production | 16,790,000
lb
|
Production Hrs. Annual | 3,600
hrs
|
Location (State) | Oregon |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $149,501 | 4,359,320 |
kWh
|
$0.034 |
Electricity Demand | $31,907 | 113,280 |
kW-mo/yr
|
$0.28 |
Electricity Fees | $5,027 | - |
|
- |
Natural Gas | $24,647 | 4,924 |
MMBtu
|
$5.01 |
LPG | $7,218 | 512 |
MMBtu
|
$14.10 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $724,041 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $8,771 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Personnel Changes Savings | Primary Raw Material Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 4.441: Install automatic packing equipment | $423,000 | $140,000 | - | - | - | $437,000 | - | $(-14,000.0) | |
02 | 4.441: Install automatic packing equipment | $91,000 | $95,000 | - | - | - | $101,000 | - | $(-10,000.0) | |
03 | 4.441: Install automatic packing equipment | $2,800 | $7,000 | - | - | - | $2,800 | - | - | |
04 | 2.2628: Utilize a less expensive cooling method | $198,470 | $500,000 |
$(-17,140.0)
(-504,103)
kWh
|
$(-4,680.0)
-
kW-mo/yr
|
- | - | $210,870 | $9,420 | |
05 | 2.2621: Modify refrigeration system to operate at a lower pressure | $7,150 | - |
$7,150
210,434
kWh
|
- | - | - | - | - | |
06 | 2.3212: Optimize plant power factor | $1,621 | $4,800 | - | - | $1,621 | - | - | - | |
TOTAL RECOMMENDED | $724,041 | $746,800 |
$(-9,990.0)
(-293,669)
kWh
|
$(-4,680.0)
-
kW-mo/yr
|
$1,621 | $540,800 | $210,870 | $(-14,580.0) | ||
TOTAL IMPLEMENTED | $8,771 | $4,800 |
$7,150
210,434
kWh
|
- | $1,621 | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Personnel Changes Savings | Primary Raw Material Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs