| Assessment Year | 2002 |
|---|---|
| Principal Product | Kaolin |
| NAICS |
n/a
|
| SIC | 3295: Minerals and Earths, Ground or Otherwise Treated |
| Sales Range | $50 M to 100M |
| # of Employees | 250 |
| Plant Area |
1,761,000
ft2
|
| Annual Production | 721,000
ton
|
| Production Hrs. Annual | 8,568
hrs
|
| Location (State) | Georgia |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $3,381,206 | 87,034,857 |
kWh
|
$0.039 |
| Natural Gas | $9,474,706 | 1,661,244 |
MMBtu
|
$5.70 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $7,077,920 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $3,996,018 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Administrative Changes Savings | Primary Raw Material Savings | Water Consumption Savings |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.8113: Purchase gas directly from a contract gas supplier | $563,200 | $1,563,200 | - | - | - | - | $563,200 | - | - | |
| 02 | 2.8114: Change rate schedules or other changes in utility service | $1,807,000 | - | - | - | - | - | $1,807,000 | - | - | |
| 03 | 2.3417: Use waste heat with a closed-cycle gas turbine-generator set to cogenerate electricity and heat | $1,527,000 | $4,140,000 |
$3,379,000
77,112,000
kWh
|
- | - |
$(-1,852,000.0)
-
MMBtu
|
- | - | - | |
| 04 | 2.5194: Redesign process | $2,159,550 | - | - | - | - |
$3,304,000
-
MMBtu
|
- | $(-1,167,200.0) |
$22,750
-
Tgal
|
|
| 05 | 2.4322: Use or replace with energy efficient substitutes | $165,202 | - |
$91,234
3,770,000
kWh
|
$64,617
-
kW-mo/yr
|
$9,351 | - | - | - | - | |
| 06 | 2.2314: Replace heat treating oven with more efficient unit | $679,000 | $250,000 | - | - | - |
$679,000
-
MMBtu
|
- | - | - | |
| 07 | 2.2511: Insulate bare equipment | $147,500 | $181,000 | - | - | - |
$147,500
-
MMBtu
|
- | - | - | |
| 08 | 2.4133: Use most efficient type of electric motors | $29,468 | $321,854 |
$15,485
639,880
kWh
|
$12,219
-
kW-mo/yr
|
$1,764 | - | - | - | - | |
| TOTAL RECOMMENDED | $7,077,920 | $6,456,054 |
$3,485,719
81,521,880
kWh
|
$76,836
-
kW-mo/yr
|
$11,115 |
$2,278,500
-
MMBtu
|
$2,370,200 | $(-1,167,200.0) |
$22,750
-
Tgal
|
||
| TOTAL IMPLEMENTED | $3,996,018 | $321,854 |
$15,485
639,880
kWh
|
$12,219
-
kW-mo/yr
|
$1,764 |
$3,304,000
-
MMBtu
|
$1,807,000 | $(-1,167,200.0) |
$22,750
-
Tgal
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Administrative Changes Savings | Primary Raw Material Savings | Water Consumption Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs