Assessment Year | 1999 |
---|---|
Principal Product | Aluminum die-castings |
NAICS |
n/a
|
SIC | 3363: Aluminum Die-Castings |
Sales Range | $10 M to 50M |
# of Employees | 170 |
Plant Area |
85,000
ft2
|
Annual Production | 4,800,000
lb
|
Production Hrs. Annual | 6,120
hrs
|
Location (State) | Washington |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $146,287 | 6,780,481 |
kWh
|
$0.022 |
Electricity Demand | $62,658 | 169,728 |
kW-mo/yr
|
$0.37 |
Electricity Fees | $12,512 | - |
|
- |
Natural Gas | $264,334 | 73,183 |
MMBtu
|
$3.61 |
LPG | $8,760 | 636 |
MMBtu
|
$13.77 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $86,719 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Fees Savings | Natural Gas Savings | Personnel Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.2414: Use waste heat from hot flue gases to preheat | $60,160 | $81,250 | - |
$60,160
-
MMBtu
|
- | |
02 | 2.2414: Use waste heat from hot flue gases to preheat | $6,270 | $3,200 | - |
$6,270
-
MMBtu
|
- | |
03 | 2.3212: Optimize plant power factor | $9,819 | $8,400 | $9,819 | - | - | |
04 | 2.2515: Use optimum thickness insulation | $3,970 | $950 | - |
$3,970
-
MMBtu
|
- | |
05 | 2.2514: Cover open tanks | $1,940 | $870 | - |
$1,940
-
MMBtu
|
- | |
06 | 2.2514: Cover open tanks | $2,130 | $5,385 | - |
$2,130
-
MMBtu
|
- | |
07 | 4.111: Add equipment/ operators to reduce production bottleneck | $2,430 | - | - | - | $2,430 | |
TOTAL RECOMMENDED | $86,719 | $100,055 | $9,819 |
$74,470
-
MMBtu
|
$2,430 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Fees Savings | Natural Gas Savings | Personnel Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs