ITAC Assessment: OR0352
ITAC logo
ITAC Assessment: OR0352
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1999
Principal Product Aluminum die-castings
NAICS
n/a
SIC 3363: Aluminum Die-Castings
Sales Range $10
M
to 50
M
# of Employees 170
Plant Area 85,000
ft2
Annual Production 4,800,000
lb
Production Hrs. Annual 6,120
hrs
Location (State) Washington

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $146,287 6,780,481
kWh
Electricity Demand $62,658 169,728
kW-mo/yr
Electricity Fees $12,512 -
Natural Gas $264,334 73,183
MMBtu
LPG $8,760 636
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $86,719 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Fees Savings Natural Gas Savings Personnel Changes Savings
01 2.2414: Use waste heat from hot flue gases to preheat $60,160 $81,250 - $60,160
-
MMBtu
-
02 2.2414: Use waste heat from hot flue gases to preheat $6,270 $3,200 - $6,270
-
MMBtu
-
03 2.3212: Optimize plant power factor $9,819 $8,400 $9,819 - -
04 2.2515: Use optimum thickness insulation $3,970 $950 - $3,970
-
MMBtu
-
05 2.2514: Cover open tanks $1,940 $870 - $1,940
-
MMBtu
-
06 2.2514: Cover open tanks $2,130 $5,385 - $2,130
-
MMBtu
-
07 4.111: Add equipment/ operators to reduce production bottleneck $2,430 - - - $2,430
TOTAL RECOMMENDED $86,719 $100,055 $9,819 $74,470
-
MMBtu
$2,430
TOTAL IMPLEMENTED - - - - -
Yearly Savings* Imp'd Cost* Electricity Fees Savings Natural Gas Savings Personnel Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs