Assessment Year | 1999 |
---|---|
Principal Product | Paper Rolls |
NAICS |
n/a
|
SIC | 2655: Fiber Cans, Tubes, Drums, and Similar Products |
Sales Range | $10 M to 50M |
# of Employees | 70 |
Plant Area |
50,000
ft2
|
Annual Production | 52,000,000
lb
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Washington |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $36,484 | 1,572,978 |
kWh
|
$0.023 |
Electricity Demand | $9,248 | 42,684 |
kW-mo/yr
|
$0.22 |
Electricity Fees | $2,287 | - |
|
- |
Natural Gas | $11,822 | 2,457 |
MMBtu
|
$4.81 |
LPG | $12,223 | 986 |
MMBtu
|
$12.40 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $37,830 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $446 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | LPG Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|---|
01 | 4.445: Install equipment to move product | $22,460 | $13,140 |
$(-170.0)
(-2,052)
kWh
|
$(-120.0)
-
kW-mo/yr
|
- | - | - | $22,750 | - | |
02 | 2.1332: Convert combustion equipment to burn natural gas | $6,490 | $44,000 |
$(-30.0)
(-1,172)
kWh
|
- |
$(-4,520.0)
-
MMBtu
|
$12,220
-
MMBtu
|
- | $(-1,180.0) | - | |
03 | 2.7111: Reduce illumination to minimum necessary levels | $4,284 | $65 |
$2,336
100,821
kWh
|
- | - | - | - | $75 | $1,873 | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $446 | $1,000 |
$387
16,706
kWh
|
$59
-
kW-mo/yr
|
- | - | - | - | - | |
05 | 3.6125: Sell combustible waste | $2,590 | - | - | - | - | - |
$2,590
-
lb
|
- | - | |
06 | 3.5248: Separate and recycle scrap metal to foundry or for sale | $1,560 | $9,635 |
$(-197.0)
(-1,465)
kWh
|
$(-163.0)
-
kW-mo/yr
|
- | - |
$3,230
-
lb
|
$(-1,310.0) | - | |
TOTAL RECOMMENDED | $37,830 | $67,840 |
$2,326
112,838
kWh
|
$(-224.0)
-
kW-mo/yr
|
$(-4,520.0)
-
MMBtu
|
$12,220
-
MMBtu
|
$5,820
-
lb
|
$20,335 | $1,873 | ||
TOTAL IMPLEMENTED | $446 | $1,000 |
$387
16,706
kWh
|
$59
-
kW-mo/yr
|
- | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | LPG Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs