Assessment Year | 1998 |
---|---|
Principal Product | Potato Chips |
NAICS |
n/a
|
SIC | 2096: Potato Chips, Corn Chips, and Similar Snacks |
Sales Range | $10 M to 50M |
# of Employees | 110 |
Plant Area |
n/a
|
Annual Production | 18,000,000
lb
|
Production Hrs. Annual | 4,640
hrs
|
Location (State) | Oregon |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $44,360 | 1,314,478 |
kWh
|
$0.034 |
Electricity Demand | $10,176 | 3,876 |
kW-mo/yr
|
$2.63 |
Electricity Fees | $5,635 | - |
|
- |
Natural Gas | $265,287 | 60,639 |
MMBtu
|
$4.37 |
LPG | $6,332 | 636 |
MMBtu
|
$9.96 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $272,866 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $14,000 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Personnel Changes Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|
01 | 4.321: Optimize production lot sizes and inventories | $14,000 | $1,630 | - | - | - | $14,000 | |
02 | 4.441: Install automatic packing equipment | $229,748 | $79,349 |
$(-396.0)
(-8,792)
kWh
|
- | $230,144 | - | |
03 | 4.441: Install automatic packing equipment | $6,574 | $15,045 |
$(-48.0)
(-1,465)
kWh
|
- | $6,622 | - | |
04 | 2.2511: Insulate bare equipment | $9,244 | $1,831 | - |
$9,244
-
MMBtu
|
- | - | |
05 | 2.2437: Recover waste heat from equipment | $11,400 | $12,250 | - |
$11,400
-
MMBtu
|
- | - | |
06 | 2.2515: Use optimum thickness insulation | $1,900 | $1,810 | - |
$1,900
-
MMBtu
|
- | - | |
TOTAL RECOMMENDED | $272,866 | $111,915 |
$(-444.0)
(-10,257)
kWh
|
$22,544
-
MMBtu
|
$236,766 | $14,000 | ||
TOTAL IMPLEMENTED | $14,000 | $1,630 | - | - | - | $14,000 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Personnel Changes Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs