ITAC Assessment: OR0338
ITAC logo
ITAC Assessment: OR0338
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1998
Principal Product Potato Chips
NAICS
n/a
SIC 2096: Potato Chips, Corn Chips, and Similar Snacks
Sales Range $10
M
to 50
M
# of Employees 110
Plant Area
n/a
Annual Production 18,000,000
lb
Production Hrs. Annual 4,640
hrs
Location (State) Oregon

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $44,360 1,314,478
kWh
Electricity Demand $10,176 3,876
kW-mo/yr
Electricity Fees $5,635 -
Natural Gas $265,287 60,639
MMBtu
LPG $6,332 636
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $272,866 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $14,000

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Personnel Changes Savings Administrative Changes Savings
01 4.321: Optimize production lot sizes and inventories $14,000 $1,630 - - - $14,000
02 4.441: Install automatic packing equipment $229,748 $79,349 $(-396.0)
(-8,792)
kWh
- $230,144 -
03 4.441: Install automatic packing equipment $6,574 $15,045 $(-48.0)
(-1,465)
kWh
- $6,622 -
04 2.2511: Insulate bare equipment $9,244 $1,831 - $9,244
-
MMBtu
- -
05 2.2437: Recover waste heat from equipment $11,400 $12,250 - $11,400
-
MMBtu
- -
06 2.2515: Use optimum thickness insulation $1,900 $1,810 - $1,900
-
MMBtu
- -
TOTAL RECOMMENDED $272,866 $111,915 $(-444.0)
(-10,257)
kWh
$22,544
-
MMBtu
$236,766 $14,000
TOTAL IMPLEMENTED $14,000 $1,630 - - - $14,000
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Personnel Changes Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs