Assessment Year | 2019 |
---|---|
Principal Product | Intermediate bulk containers |
NAICS | 332313: Plate Work Manufacturing |
SIC | 3443: Fabricated Plate Work (Boiler Shops) |
Sales Range | $10 M to 50M |
# of Employees | 200 |
Plant Area |
195,000
ft2
|
Annual Production | 10,650
units
|
Production Hrs. Annual | 2,416
hrs
|
Location (State) | Texas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $54,221 | 1,437,089 |
kWh
|
$0.038 | |
Electricity Demand | $48,094 | 5,773 |
kW-mo/yr
|
$8.33 | |
Electricity Fees | $4,082 | - |
|
- | |
Natural Gas | $26,060 | 3,098 |
MMBtu
|
$8.41 | |
Waste Disposal Costs | |||||
Water Disposal | $44,685 | 406,226 |
Tgal
|
$0.11 | |
TOTAL YEARLY COSTS | $177,142 | ||||
RECOMMENDED SAVINGS* | $39,777 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | $2,858 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Water Disposal Savings | Personnel Changes Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $17,060 | $25,000 | - | - | - |
$(-14,220.0)
-
MMBtu
|
$31,280
-
Tgal
|
- | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $11,552 | $12,220 |
$6,170
166,757
kWh
|
$5,382
-
kW-mo/yr
|
- | - | - | - | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,768 | $1,000 |
$859
23,223
kWh
|
$909
-
kW-mo/yr
|
- | - | - | - | |
04 | 2.4231: Reduce the pressure of compressed air to the minimum required | $13 | $10 |
$13
346
kWh
|
- | - | - | - | - | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,077 | $480 |
$140
3,784
kWh
|
$38
-
kW-mo/yr
|
- | - | - | $899 | |
06 | 2.4314: Use synthetic lubricant | $92 | $40 |
$34
910
kWh
|
$58
-
kW-mo/yr
|
- | - | - | - | |
07 | 2.8123: Pay utility bills on time | $1,751 | - | - | - | $1,751 | - | - | - | |
08 | 2.3212: Optimize plant power factor | $6,464 | $18,747 | - |
$6,464
-
kW-mo/yr
|
- | - | - | - | |
TOTAL RECOMMENDED | $39,777 | $57,497 |
$7,216
195,020
kWh
|
$12,851
-
kW-mo/yr
|
$1,751 |
$(-14,220.0)
-
MMBtu
|
$31,280
-
Tgal
|
$899 | ||
TOTAL IMPLEMENTED | $2,858 | $1,490 |
$1,012
27,353
kWh
|
$947
-
kW-mo/yr
|
- | - | - | $899 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Water Disposal Savings | Personnel Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs