ITAC Assessment: OR0329
ITAC logo
ITAC Assessment: OR0329
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1998
Principal Product Vacuum Formed Plastic Parts
NAICS
n/a
SIC 3089: Plastics Products, Not Elsewhere Classified
Sales Range $1
M
to 5
M
# of Employees 30
Plant Area 64,400
ft2
Annual Production 490,847
pieces
Production Hrs. Annual 30
hrs
Location (State) Washington

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $35,337 1,732,708
kWh
Electricity Demand $33,680 8,756
kW-mo/yr
Electricity Fees $336 -
Natural Gas $3,395 540
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $48,802 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $1,950

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings
01 4.421: Modify current incentive program $21,200 $22,600 - - - $21,200
02 4.625: Develop standard operating procedures $1,950 $1,140 - - - $1,950
03 2.4224: Upgrade controls on compressors $2,982 $1,000 $1,457
71,512
kWh
$1,525
-
kW-mo/yr
- -
04 2.1311: Replace electrically-operated equipment with fossil fuel equipment $22,670 $239,200 $11,220
550,410
kWh
$16,900
-
kW-mo/yr
$(-5,450.0)
-
MMBtu
-
TOTAL RECOMMENDED $48,802 $263,940 $12,677
621,922
kWh
$18,425
-
kW-mo/yr
$(-5,450.0)
-
MMBtu
$23,150
TOTAL IMPLEMENTED $1,950 $1,140 - - - $1,950
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs