| Assessment Year | 1998 |
|---|---|
| Principal Product | Recycled Aluminum |
| NAICS |
n/a
|
| SIC | 3341: Secondary Smelting and Refining of Nonferrous Metals |
| Sales Range | $10 M to 50M |
| # of Employees | 24 |
| Plant Area |
n/a
|
| Annual Production | 38,131,000
lb
|
| Production Hrs. Annual | 3,680
hrs
|
| Location (State) | Oregon |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $165,449 | 5,047,186 |
kWh
|
$0.033 |
| Electricity Demand | $47,774 | 178,044 |
kW-mo/yr
|
$0.27 |
| Electricity Fees | $(-2,746.0) | - |
|
- |
| Natural Gas | $387,729 | 123,328 |
MMBtu
|
$3.14 |
| LPG | $23,654 | 2,322 |
MMBtu
|
$10.19 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $91,581 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | LPG Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.2511: Insulate bare equipment | $60,872 | $1,851 | - | - |
$60,872
-
MMBtu
|
- | - | - | |
| 02 | 2.1113: Reduce combustion air flow to optimum | $8,820 | - | - | - |
$8,820
-
MMBtu
|
- | - | - | |
| 03 | 2.1332: Convert combustion equipment to burn natural gas | $16,110 | $138,600 |
$(-570.0)
(-17,292)
kWh
|
$(-1,220.0)
-
kW-mo/yr
|
$(-5,700.0)
-
MMBtu
|
$23,600
-
MMBtu
|
- | - | |
| 04 | 2.7124: Make a practice of turning off lights when not needed | $3,189 | - |
$2,452
74,736
kWh
|
- | - | - | $61 | $676 | |
| 05 | 4.513: Re-arrange equipment layout to reduce labor costs | $2,590 | $15,000 | - | - |
$40
-
MMBtu
|
- | $2,550 | - | |
| TOTAL RECOMMENDED | $91,581 | $155,451 |
$1,882
57,444
kWh
|
$(-1,220.0)
-
kW-mo/yr
|
$64,032
-
MMBtu
|
$23,600
-
MMBtu
|
$2,611 | $676 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | - | - | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs