ITAC Assessment: OR0321
ITAC logo
ITAC Assessment: OR0321
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1998
Principal Product Recycled Aluminum
NAICS
n/a
SIC 3341: Secondary Smelting and Refining of Nonferrous Metals
Sales Range $10
M
to 50
M
# of Employees 24
Plant Area
n/a
Annual Production 38,131,000
lb
Production Hrs. Annual 3,680
hrs
Location (State) Oregon

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $165,449 5,047,186
kWh
Electricity Demand $47,774 178,044
kW-mo/yr
Electricity Fees $(-2,746.0) -
Natural Gas $387,729 123,328
MMBtu
LPG $23,654 2,322
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $91,581 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings LPG Savings Personnel Changes Savings Ancillary Material Cost Savings
01 2.2511: Insulate bare equipment $60,872 $1,851 - - $60,872
-
MMBtu
- - -
02 2.1113: Reduce combustion air flow to optimum $8,820 - - - $8,820
-
MMBtu
- - -
03 2.1332: Convert combustion equipment to burn natural gas $16,110 $138,600 $(-570.0)
(-17,292)
kWh
$(-1,220.0)
-
kW-mo/yr
$(-5,700.0)
-
MMBtu
$23,600
-
MMBtu
- -
04 2.7124: Make a practice of turning off lights when not needed $3,189 - $2,452
74,736
kWh
- - - $61 $676
05 4.513: Re-arrange equipment layout to reduce labor costs $2,590 $15,000 - - $40
-
MMBtu
- $2,550 -
TOTAL RECOMMENDED $91,581 $155,451 $1,882
57,444
kWh
$(-1,220.0)
-
kW-mo/yr
$64,032
-
MMBtu
$23,600
-
MMBtu
$2,611 $676
TOTAL IMPLEMENTED - - - - - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs