ITAC Assessment: OR0310
ITAC logo
ITAC Assessment: OR0310
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1997
Principal Product Rotational Molded Plastics
NAICS
n/a
SIC 3089: Plastics Products, Not Elsewhere Classified
Sales Range $1
M
to 5
M
# of Employees 58
Plant Area 45,000
ft2
Annual Production 1,848,057
lb
Production Hrs. Annual 7,488
hrs
Location (State) Washington

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $16,073 837,339
kWh
Electricity Demand $6,638 21,864
kW-mo/yr
Electricity Fees $1,770 -
Natural Gas $56,374 14,840
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $30,896 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $13,334

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings Personnel Changes Savings Ancillary Material Cost Savings
01 3.1163: Use plastic pallets instead of wood $11,530 $1,830 - - - $430
-
lb
$(-2,340.0) $13,440
02 4.423: Move product using mechanical means $9,625 $14,810 $(-340.0)
(-13,189)
kWh
$(-85.0)
-
kW-mo/yr
- - $10,050 -
03 2.2511: Insulate bare equipment $4,309 $2,320 - - $4,309
-
MMBtu
- - -
04 2.2437: Recover waste heat from equipment $2,930 $8,750 $665
34,584
kWh
$2,265
-
kW-mo/yr
- - - -
05 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,635 $2,500 $852
39,859
kWh
$783
-
kW-mo/yr
- - - -
06 2.4231: Reduce the pressure of compressed air to the minimum required $169 $670 $80
4,103
kWh
$89
-
kW-mo/yr
- - - -
07 2.4133: Use most efficient type of electric motors $698 $2,017 $473
24,619
kWh
$225
-
kW-mo/yr
- - - -
TOTAL RECOMMENDED $30,896 $32,897 $1,730
89,976
kWh
$3,277
-
kW-mo/yr
$4,309
-
MMBtu
$430
-
lb
$7,710 $13,440
TOTAL IMPLEMENTED $13,334 $5,000 $932
43,962
kWh
$872
-
kW-mo/yr
- $430
-
lb
$(-2,340.0) $13,440
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings Personnel Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs