ITAC Assessment: OR0304
ITAC logo
ITAC Assessment: OR0304
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1997
Principal Product Beer
NAICS
n/a
SIC 2082: Malt Beverages
Sales Range $10
M
to 50
M
# of Employees 132
Plant Area 120,200
ft2
Annual Production 117,904
bbl
Production Hrs. Annual 0
hrs
Location (State) Oregon

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $153,791 3,095,545
kWh
Electricity Demand $2,382 9,240
kW-mo/yr
Electricity Fees $117 -
Natural Gas $114,778 32,009
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $49,946 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $36,535

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Water Disposal Savings Water Consumption Savings
01 2.8114: Change rate schedules or other changes in utility service $13,502 - - - $13,502 - - -
02 2.3212: Optimize plant power factor $1,070 $3,200 - - $1,070 - - -
03 2.1231: Establish burner maintenance schedule for boilers $9,530 - $960
21,981
kWh
$680
-
kW-mo/yr
- $7,890
-
MMBtu
- -
04 2.1233: Analyze flue gas for proper air/fuel ratio $450 $500 - - - $450
-
MMBtu
- -
05 2.2621: Modify refrigeration system to operate at a lower pressure $4,881 $1,560 $4,881
112,251
kWh
- - - - -
06 2.2621: Modify refrigeration system to operate at a lower pressure $4,300 - $4,300
99,062
kWh
- - - - -
07 2.4133: Use most efficient type of electric motors $2,988 $5,910 $2,605
60,082
kWh
$383
-
kW-mo/yr
- - - -
08 3.4151: Minimize water usage $4,000 - - - - - $4,000
-
Tgal
-
09 3.5311: Recover and reuse waste material - $250 - - - - - -
10 3.4111: Use closed cycle process to minimize waste water production $3,460 $610 - - - - $3,460
-
Tgal
-
11 3.4111: Use closed cycle process to minimize waste water production $3,460 $910 - - - - $3,460
-
Tgal
-
12 3.4151: Minimize water usage $2,305 - $391
11,723
kWh
- - - $1,526
-
Tgal
$388
-
Tgal
TOTAL RECOMMENDED $49,946 $12,940 $13,137
305,099
kWh
$1,063
-
kW-mo/yr
$14,572 $8,340
-
MMBtu
$12,446
-
Tgal
$388
-
Tgal
TOTAL IMPLEMENTED $36,535 $7,020 $8,256
192,848
kWh
$1,063
-
kW-mo/yr
$13,502 $8,340
-
MMBtu
$4,986
-
Tgal
$388
-
Tgal
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Water Disposal Savings Water Consumption Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs