Assessment Year | 1997 |
---|---|
Principal Product | Dehydrated Soup Mix |
NAICS |
n/a
|
SIC | 2099: Food Preparations, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 50 |
Plant Area |
75,000
ft2
|
Annual Production | 1,066
ton
|
Production Hrs. Annual | 3,280
hrs
|
Location (State) | Washington |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $18,053 | 843,787 |
kWh
|
$0.021 |
Electricity Demand | $15,448 | 3,492 |
kW-mo/yr
|
$4.42 |
Electricity Fees | $2,476 | - |
|
- |
Natural Gas | $7,596 | 1,508 |
MMBtu
|
$5.04 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $53,532 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $3,991 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Primary Raw Material Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|---|
01 | 4.213: Purchase material from supplier in customized packaging | $42,600 | - | - | - | - | - | - | $42,600 | - | |
02 | 4.221: Use only amount of packaging material necessary | $400 | - | - | - | - | - | - | - | $400 | |
03 | 3.1162: Use less wasteful packaging | $4,720 | - | - | - | - |
$(-80.0)
-
lb
|
- | - | $4,800 | |
04 | 3.5314: Use in-process recycling whenever possible | $103 | - | - | - | - |
$103
-
lb
|
- | - | - | |
05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,358 | - |
$810
37,808
kWh
|
$548
-
kW-mo/yr
|
- | - | - | - | - | |
06 | 2.4225: Install common header on compressors | $1,105 | $120 |
$658
30,774
kWh
|
$447
-
kW-mo/yr
|
- | - | - | - | - | |
07 | 2.7121: Utilize daylight whenever possible in lieu of artificial light | $1,042 | $1,000 |
$715
33,411
kWh
|
- | - | - | $27 | - | $300 | |
08 | 2.4133: Use most efficient type of electric motors | $1,025 | $1,767 |
$594
27,843
kWh
|
$431
-
kW-mo/yr
|
- | - | - | - | - | |
09 | 2.3212: Optimize plant power factor | $1,179 | $2,200 | - | - | $1,179 | - | - | - | - | |
TOTAL RECOMMENDED | $53,532 | $5,087 |
$2,777
129,836
kWh
|
$1,426
-
kW-mo/yr
|
$1,179 |
$23
-
lb
|
$27 | $42,600 | $5,500 | ||
TOTAL IMPLEMENTED | $3,991 | $1,887 |
$2,062
96,425
kWh
|
$1,426
-
kW-mo/yr
|
- |
$103
-
lb
|
- | - | $400 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Primary Raw Material Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs