Assessment Year | 1997 |
---|---|
Principal Product | Paper Boxes |
NAICS |
n/a
|
SIC | 2657: Folding Paperboard Boxes, Including Sanitary |
Sales Range | $10 M to 50M |
# of Employees | 52 |
Plant Area |
105,000
ft2
|
Annual Production | 0
units
|
Production Hrs. Annual | 4,000
hrs
|
Location (State) | Oregon |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $52,335 | 1,408,265 |
kWh
|
$0.037 |
Electricity Demand | $18,354 | 58,848 |
kW-mo/yr
|
$0.31 |
Electricity Fees | $2,142 | - |
|
- |
Natural Gas | $10,026 | 2,142 |
MMBtu
|
$4.68 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $159,155 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $158,825 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Personnel Changes Savings | Primary Raw Material Savings | Ancillary Material Cost Savings | Primary Product Savings |
---|---|---|---|---|---|---|---|---|---|---|---|---|
01 | 4.711: Initiate a total quality management program | $154,770 | - | - | - | - | - | $68,000 | $(-216,000.0) | $2,770 | $300,000 | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,260 | $2,500 |
$2,260
66,530
kWh
|
- | - | - | - | - | - | - | |
03 | 2.7124: Make a practice of turning off lights when not needed | $583 | - |
$393
11,430
kWh
|
- | - | - | $61 | - | $129 | - | |
04 | 2.7121: Utilize daylight whenever possible in lieu of artificial light | $632 | $105 |
$306
9,086
kWh
|
$86
-
kW-mo/yr
|
- | - | $21 | - | $219 | - | |
05 | 2.1233: Analyze flue gas for proper air/fuel ratio | $580 | $1,500 | - | - | - |
$580
-
MMBtu
|
- | - | - | - | |
06 | 2.3212: Optimize plant power factor | $330 | $1,300 | - | - | $330 | - | - | - | - | - | |
TOTAL RECOMMENDED | $159,155 | $5,405 |
$2,959
87,046
kWh
|
$86
-
kW-mo/yr
|
$330 |
$580
-
MMBtu
|
$68,082 | $(-216,000.0) | $3,118 | $300,000 | ||
TOTAL IMPLEMENTED | $158,825 | $4,105 |
$2,959
87,046
kWh
|
$86
-
kW-mo/yr
|
- |
$580
-
MMBtu
|
$68,082 | $(-216,000.0) | $3,118 | $300,000 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Personnel Changes Savings | Primary Raw Material Savings | Ancillary Material Cost Savings | Primary Product Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs