| Assessment Year | 1997 |
|---|---|
| Principal Product | Steamed Rice |
| NAICS |
n/a
|
| SIC | 2044: Rice Milling |
| Sales Range | $10 M to 50M |
| # of Employees | 12 |
| Plant Area |
n/a
|
| Annual Production | 18,900,000
lb
|
| Production Hrs. Annual | 2,626
hrs
|
| Location (State) | Oregon |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $39,339 | 1,114,596 |
kWh
|
$0.035 |
| Electricity Demand | $9,504 | 2,340 |
kW-mo/yr
|
$4.06 |
| Electricity Fees | $126 | - |
|
- |
| Natural Gas | $20,021 | 4,335 |
MMBtu
|
$4.62 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $12,108 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.6218: Turn off equipment when not in use | $3,530 | - |
$3,530
105,803
kWh
|
- | - | - | - | - | |
| 02 | 2.4133: Use most efficient type of electric motors | $2,121 | $3,853 |
$1,643
48,359
kWh
|
$478
-
kW-mo/yr
|
- | - | - | - | |
| 03 | 2.1233: Analyze flue gas for proper air/fuel ratio | $1,160 | $500 | - | - |
$1,160
-
MMBtu
|
- | - | - | |
| 04 | 2.7124: Make a practice of turning off lights when not needed | $171 | - |
$133
3,810
kWh
|
- | - | - | $17 | $21 | |
| 05 | 4.652: Replace existing equipment with more suitable substitutes | $2,706 | $8,250 | - | - | - |
$2,706
-
Tgal
|
- | - | |
| 06 | 4.652: Replace existing equipment with more suitable substitutes | $2,420 | $130 | - | - |
$2,350
-
MMBtu
|
$70
-
Tgal
|
- | - | |
| TOTAL RECOMMENDED | $12,108 | $12,733 |
$5,306
157,972
kWh
|
$478
-
kW-mo/yr
|
$3,510
-
MMBtu
|
$2,776
-
Tgal
|
$17 | $21 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Personnel Changes Savings | Ancillary Material Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs