ITAC Assessment: OR0297
ITAC logo
ITAC Assessment: OR0297
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1997
Principal Product Steamed Rice
NAICS
n/a
SIC 2044: Rice Milling
Sales Range $10
M
to 50
M
# of Employees 12
Plant Area
n/a
Annual Production 18,900,000
lb
Production Hrs. Annual 2,626
hrs
Location (State) Oregon

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $39,339 1,114,596
kWh
Electricity Demand $9,504 2,340
kW-mo/yr
Electricity Fees $126 -
Natural Gas $20,021 4,335
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $12,108 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Personnel Changes Savings Ancillary Material Cost Savings
01 2.6218: Turn off equipment when not in use $3,530 - $3,530
105,803
kWh
- - - - -
02 2.4133: Use most efficient type of electric motors $2,121 $3,853 $1,643
48,359
kWh
$478
-
kW-mo/yr
- - - -
03 2.1233: Analyze flue gas for proper air/fuel ratio $1,160 $500 - - $1,160
-
MMBtu
- - -
04 2.7124: Make a practice of turning off lights when not needed $171 - $133
3,810
kWh
- - - $17 $21
05 4.652: Replace existing equipment with more suitable substitutes $2,706 $8,250 - - - $2,706
-
Tgal
- -
06 4.652: Replace existing equipment with more suitable substitutes $2,420 $130 - - $2,350
-
MMBtu
$70
-
Tgal
- -
TOTAL RECOMMENDED $12,108 $12,733 $5,306
157,972
kWh
$478
-
kW-mo/yr
$3,510
-
MMBtu
$2,776
-
Tgal
$17 $21
TOTAL IMPLEMENTED - - - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Personnel Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs