ITAC Assessment: OR0291
ITAC logo
ITAC Assessment: OR0291
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1997
Principal Product potato chips, corn chips, nuts
NAICS
n/a
SIC 2096: Potato Chips, Corn Chips, and Similar Snacks
Sales Range $10
M
to 50
M
# of Employees 71
Plant Area 41,250
ft2
Annual Production 4,719,113
lb
Production Hrs. Annual 8,400
hrs
Location (State) Oregon

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $33,921 746,190
kWh
Electricity Demand $4,511 2,069
kW-mo/yr
Electricity Fees $1,636 -
Natural Gas $94,598 23,088
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $68,554 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $6,721

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Solid Waste (non-haz) Savings Personnel Changes Savings Ancillary Material Cost Savings Water Consumption Savings
01 3.1191: Change procedures / equipment / operating conditions $35,946 $240 - - - - $35,946
-
lb
- - -
02 3.6123: Burn wood by-products for heat $5,024 - - - - - $5,024
-
lb
- - -
03 3.6192: Use a less expensive method of waste removal $814 - - - - - $814
-
lb
- - -
04 3.4114: Replace city water with recycled water via cooling tower $14,628 $3,460 $(-248.0)
(-7,034)
kWh
$(-51.0)
-
kW-mo/yr
- $11,563
-
Tgal
- - - $3,364
-
Tgal
05 3.4115: Recover and reuse cooling water $1,749 $1,300 - - - $1,355
-
Tgal
- - - $394
-
Tgal
06 3.5315: Lease / purchase baler; sell cardboard to recycler $6,204 $10,103 $(-27.0)
(-879)
kWh
$(-385.0)
-
kW-mo/yr
- - $4,812
-
lb
$1,804 - -
07 2.7142: Utilize higher efficiency lamps and/or ballasts $716 $1,471 $522
8,206
kWh
- - - - $122 $72 -
08 2.4133: Use most efficient type of electric motors $883 $2,029 $692
19,343
kWh
$191
-
kW-mo/yr
- - - - - -
09 2.1221: Replace obsolete burners with more efficient ones $2,590 $11,350 - - $2,590
-
MMBtu
- - - - -
TOTAL RECOMMENDED $68,554 $29,953 $939
19,636
kWh
$(-245.0)
-
kW-mo/yr
$2,590
-
MMBtu
$12,918
-
Tgal
$46,596
-
lb
$1,926 $72 $3,758
-
Tgal
TOTAL IMPLEMENTED $6,721 $2,029 $692
19,343
kWh
$191
-
kW-mo/yr
- - $5,838
-
lb
- - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Solid Waste (non-haz) Savings Personnel Changes Savings Ancillary Material Cost Savings Water Consumption Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs