Assessment Year | 2020 |
---|---|
Principal Product | Medical Equipment |
NAICS | 339112: Surgical and Medical Instrument Manufacturing |
SIC | 3841: Surgical and Medical Instruments and Apparatus |
Sales Range | $10 M to 50M |
# of Employees | 100 |
Plant Area |
28,000
ft2
|
Annual Production | 5,000,000
lb
|
Production Hrs. Annual | 2,210
hrs
|
Location (State) | Massachusetts |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $169,906 | 1,302,112 |
kWh
|
$0.13 | |
Electricity Demand | $68,263 | 3,070 |
kW-mo/yr
|
$22.24 | |
Electricity Fees | $1,470 | - |
|
- | |
Natural Gas | $11,380 | 847 |
MMBtu
|
$13.44 | |
Waste Disposal Costs | |||||
Water Usage | $29,694 | 16,048 |
Tgal
|
$1.85 | |
TOTAL YEARLY COSTS | $280,713 | ||||
RECOMMENDED SAVINGS* | $93,779 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.9114: Use solar heat to make electricty | $60,067 | $253,810 |
$40,751
313,467
kWh
|
- | - | $19,316 | |
02 | 2.7224: Reduce space conditioning during non-working hours | $20,202 | $27,887 |
$19,141
147,244
kWh
|
- |
$1,061
-
MMBtu
|
- | |
03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $5,915 | $1,000 |
$5,915
45,494
kWh
|
- | - | - | |
04 | 2.3212: Optimize plant power factor | $4,535 | $8,890 | - |
$4,535
-
kW-mo/yr
|
- | - | |
05 | 2.7241: Install outside air damper / economizer on hvac unit | $3,060 | $9,957 |
$1,757
13,515
kWh
|
- |
$1,303
-
MMBtu
|
- | |
TOTAL RECOMMENDED | $93,779 | $301,544 |
$67,564
519,720
kWh
|
$4,535
-
kW-mo/yr
|
$2,364
-
MMBtu
|
$19,316 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs