ITAC Assessment: OR0289
ITAC logo
ITAC Assessment: OR0289
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1997
Principal Product Sand, Gravel, Concrete
NAICS
n/a
SIC 3281: Cut Stone and Stone Products
Sales Range $5
M
to 10
M
# of Employees 50
Plant Area 871,200
ft2
Annual Production 353,284
ton
Production Hrs. Annual 2,500
hrs
Location (State) Washington

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $65,498 2,880,715
kWh
Electricity Demand $42,580 9,853
kW-mo/yr
Electricity Fees $9,099 -
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $156,664 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $2,495

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Personnel Changes Savings Primary Raw Material Savings Ancillary Material Cost Savings Primary Product Savings
01 3.5311: Recover and reuse waste material $82,720 $56,000 - - - $96,990 $(-14,270.0) -
02 2.5194: Redesign process $42,400 $4,300 - $(-2,600.0)
-
kW-mo/yr
$45,000 - - -
03 4.112: Replace old machine with new automatic multi-station tool $25,646 $85,000 $(-4,315.0)
(-201,055)
kWh
$(-4,822.0)
-
kW-mo/yr
- - - $34,783
04 2.4133: Use most efficient type of electric motors $2,495 $1,479 $1,348
62,720
kWh
$1,147
-
kW-mo/yr
- - - -
05 2.7142: Utilize higher efficiency lamps and/or ballasts $3,403 $13,550 $1,582
73,857
kWh
$1,734
-
kW-mo/yr
- - $87 -
TOTAL RECOMMENDED $156,664 $160,329 $(-1,385.0)
(-64,478)
kWh
$(-4,541.0)
-
kW-mo/yr
$45,000 $96,990 $(-14,183.0) $34,783
TOTAL IMPLEMENTED $2,495 $1,479 $1,348
62,720
kWh
$1,147
-
kW-mo/yr
- - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs