Assessment Year | 1997 |
---|---|
Principal Product | Sand, Gravel, Concrete |
NAICS |
n/a
|
SIC | 3281: Cut Stone and Stone Products |
Sales Range | $5 M to 10M |
# of Employees | 50 |
Plant Area |
871,200
ft2
|
Annual Production | 353,284
ton
|
Production Hrs. Annual | 2,500
hrs
|
Location (State) | Washington |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $65,498 | 2,880,715 |
kWh
|
$0.023 |
Electricity Demand | $42,580 | 9,853 |
kW-mo/yr
|
$4.32 |
Electricity Fees | $9,099 | - |
|
- |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $156,664 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $2,495 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | Primary Raw Material Savings | Ancillary Material Cost Savings | Primary Product Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 3.5311: Recover and reuse waste material | $82,720 | $56,000 | - | - | - | $96,990 | $(-14,270.0) | - | |
02 | 2.5194: Redesign process | $42,400 | $4,300 | - |
$(-2,600.0)
-
kW-mo/yr
|
$45,000 | - | - | - | |
03 | 4.112: Replace old machine with new automatic multi-station tool | $25,646 | $85,000 |
$(-4,315.0)
(-201,055)
kWh
|
$(-4,822.0)
-
kW-mo/yr
|
- | - | - | $34,783 | |
04 | 2.4133: Use most efficient type of electric motors | $2,495 | $1,479 |
$1,348
62,720
kWh
|
$1,147
-
kW-mo/yr
|
- | - | - | - | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,403 | $13,550 |
$1,582
73,857
kWh
|
$1,734
-
kW-mo/yr
|
- | - | $87 | - | |
TOTAL RECOMMENDED | $156,664 | $160,329 |
$(-1,385.0)
(-64,478)
kWh
|
$(-4,541.0)
-
kW-mo/yr
|
$45,000 | $96,990 | $(-14,183.0) | $34,783 | ||
TOTAL IMPLEMENTED | $2,495 | $1,479 |
$1,348
62,720
kWh
|
$1,147
-
kW-mo/yr
|
- | - | - | - |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs