ITAC Assessment: OR0287
ITAC logo
ITAC Assessment: OR0287
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1997
Principal Product Manufactured Homes
NAICS
n/a
SIC 2452: Prefabricated Wood Buildings and Components
Sales Range $50
M
to 100
M
# of Employees 458
Plant Area 240,000
ft2
Annual Production 2,854
pieces
Production Hrs. Annual 5,145
hrs
Location (State) Oregon

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $82,999 2,783,705
kWh
Electricity Demand $2,778 609
kW-mo/yr
Electricity Fees $168 -
Natural Gas $63,782 13,296
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $61,990 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $2,250

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Other Liquid (haz) Savings Solid Waste (non-haz) Savings Personnel Changes Savings
01 3.1172: Revise raw material specs $32,300 $104,000 - - - - $32,300
-
lb
-
02 3.1175: Use a different or recycled raw material $17,270 - - - - - $2,570
-
lb
$14,700
03 3.5311: Recover and reuse waste material $480 - - - - $480
-
gal
- -
04 3.5248: Separate and recycle scrap metal to foundry or for sale $260 - - - - - $260
-
lb
-
05 2.4133: Use most efficient type of electric motors $1,770 $2,885 $1,260
46,600
kWh
$510
-
kW-mo/yr
- - - -
06 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves - $2,000 - - - - - -
07 2.4111: Utilize energy-efficient belts and other improved mechanisms $450 $2,000 $320
12,016
kWh
$130
-
kW-mo/yr
- - - -
08 2.2492: Use "heat wheel" or other heat exchanger to cross-exchange building exhaust air with make-up air $9,460 $134,000 $3,350
123,974
kWh
$1,340
-
kW-mo/yr
$4,770
-
MMBtu
- - -
TOTAL RECOMMENDED $61,990 $244,885 $4,930
182,590
kWh
$1,980
-
kW-mo/yr
$4,770
-
MMBtu
$480
-
gal
$35,130
-
lb
$14,700
TOTAL IMPLEMENTED $2,250 $4,885 $1,260
46,600
kWh
$510
-
kW-mo/yr
- $480
-
gal
- -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Other Liquid (haz) Savings Solid Waste (non-haz) Savings Personnel Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs