ITAC Assessment: OR0286
ITAC logo
ITAC Assessment: OR0286
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1997
Principal Product Pitted Brined Cherries
NAICS
n/a
SIC 2035: Pickled Fruits and Vegetables, Vegetable Sauces and Seasonings, and Salad Dressings
Sales Range $1
M
to 5
M
# of Employees 45
Plant Area 10,000
ft2
Annual Production 8,370,100
lb
Production Hrs. Annual 2,000
hrs
Location (State) Oregon

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $65,481 1,948,710
kWh
Electricity Demand $25,274 6,648
kW-mo/yr
Electricity Fees $862 -
Natural Gas $36,181 9,749
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $20,489 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $907

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Personnel Changes Savings Ancillary Material Cost Savings
01 3.6123: Burn wood by-products for heat $907 - - - - $720 $187
02 2.8114: Change rate schedules or other changes in utility service $19,123 $16,000 - - $19,123 - -
03 2.4133: Use most efficient type of electric motors $459 $1,538 $266
13,189
kWh
$193
-
kW-mo/yr
- - -
TOTAL RECOMMENDED $20,489 $17,538 $266
13,189
kWh
$193
-
kW-mo/yr
$19,123 $720 $187
TOTAL IMPLEMENTED $907 - - - - $720 $187
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs