Assessment Year | 1996 |
---|---|
Principal Product | maraschino cherries |
NAICS |
n/a
|
SIC | 2033: Canned Fruits, Vegetables, Preserves, Jams, and Jellies |
Sales Range | $10 M to 50M |
# of Employees | 85 |
Plant Area |
10,000
ft2
|
Annual Production | 6,759,452
lb
|
Production Hrs. Annual | 5,950
hrs
|
Location (State) | Oregon |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $26,336 | 857,562 |
kWh
|
$0.031 |
Electricity Demand | $10,511 | 2,676 |
kW-mo/yr
|
$3.93 |
Natural Gas | $72,360 | 19,497 |
MMBtu
|
$3.71 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $36,759 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $36,589 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $35,224 | $10,450 |
$(-20.0)
(-879)
kWh
|
$(-36.0)
-
kW-mo/yr
|
- |
$20,400
-
lb
|
$14,880 | |
02 | 2.2136: Install / repair insulation on steam lines | $1,074 | $516 | - | - |
$1,074
-
MMBtu
|
- | - | |
03 | 2.2123: Insulate feedwater tank | $291 | $155 | - | - |
$291
-
MMBtu
|
- | - | |
04 | 2.4133: Use most efficient type of electric motors | $170 | $804 |
$97
4,689
kWh
|
$73
-
kW-mo/yr
|
- | - | - | |
TOTAL RECOMMENDED | $36,759 | $11,925 |
$77
3,810
kWh
|
$37
-
kW-mo/yr
|
$1,365
-
MMBtu
|
$20,400
-
lb
|
$14,880 | ||
TOTAL IMPLEMENTED | $36,589 | $11,121 |
$(-20.0)
(-879)
kWh
|
$(-36.0)
-
kW-mo/yr
|
$1,365
-
MMBtu
|
$20,400
-
lb
|
$14,880 |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs