ITAC Assessment: OR0281
ITAC logo
ITAC Assessment: OR0281
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1996
Principal Product powdered milk
NAICS
n/a
SIC 2023: Dry, Condensed, and Evaporated Dairy Products
Sales Range $50
M
to 100
M
# of Employees 35
Plant Area 80,000
ft2
Annual Production 80,000,000
lb
Production Hrs. Annual 8,760
hrs
Location (State) Washington

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $384,440 15,506,155
kWh
Electricity Demand $152,410 31,752
kW-mo/yr
Electricity Fees $9,062 -
Natural Gas $760,986 210,807
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $69,710 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $59,150

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings Administrative Changes Savings
01 2.1232: Keep boiler tubes clean $10,640 $800 - - $11,120
-
MMBtu
- $(-480.0)
02 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $18,000 $128,480 $18,000
726,260
kWh
- - - -
03 2.4133: Use most efficient type of electric motors $16,450 $34,810 $11,920
480,657
kWh
$4,530
-
kW-mo/yr
- - -
04 2.4111: Utilize energy-efficient belts and other improved mechanisms $3,510 $11,180 $2,620
105,803
kWh
$890
-
kW-mo/yr
- - -
05 2.2694: Use highest temperature for chilling or cold storage $7,790 $2,000 $7,790
314,478
kWh
- - - -
06 2.2694: Use highest temperature for chilling or cold storage $2,770 $5,000 $2,770
111,958
kWh
- - - -
07 2.2621: Modify refrigeration system to operate at a lower pressure $10,430 $50,000 $9,805
395,662
kWh
$625
-
kW-mo/yr
- - -
08 3.5315: Lease / purchase baler; sell cardboard to recycler $120 - - - - $120
-
lb
-
TOTAL RECOMMENDED $69,710 $232,270 $52,905
2,134,818
kWh
$6,045
-
kW-mo/yr
$11,120
-
MMBtu
$120
-
lb
$(-480.0)
TOTAL IMPLEMENTED $59,150 $225,270 $42,345
1,708,382
kWh
$6,045
-
kW-mo/yr
$11,120
-
MMBtu
$120
-
lb
$(-480.0)
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs