| Assessment Year | 1996 |
|---|---|
| Principal Product | powdered milk |
| NAICS |
n/a
|
| SIC | 2023: Dry, Condensed, and Evaporated Dairy Products |
| Sales Range | $50 M to 100M |
| # of Employees | 35 |
| Plant Area |
80,000
ft2
|
| Annual Production | 80,000,000
lb
|
| Production Hrs. Annual | 8,760
hrs
|
| Location (State) | Washington |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $384,440 | 15,506,155 |
kWh
|
$0.025 |
| Electricity Demand | $152,410 | 31,752 |
kW-mo/yr
|
$4.80 |
| Electricity Fees | $9,062 | - |
|
- |
| Natural Gas | $760,986 | 210,807 |
MMBtu
|
$3.61 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $69,710 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $59,150 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.1232: Keep boiler tubes clean | $10,640 | $800 | - | - |
$11,120
-
MMBtu
|
- | $(-480.0) | |
| 02 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $18,000 | $128,480 |
$18,000
726,260
kWh
|
- | - | - | - | |
| 03 | 2.4133: Use most efficient type of electric motors | $16,450 | $34,810 |
$11,920
480,657
kWh
|
$4,530
-
kW-mo/yr
|
- | - | - | |
| 04 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $3,510 | $11,180 |
$2,620
105,803
kWh
|
$890
-
kW-mo/yr
|
- | - | - | |
| 05 | 2.2694: Use highest temperature for chilling or cold storage | $7,790 | $2,000 |
$7,790
314,478
kWh
|
- | - | - | - | |
| 06 | 2.2694: Use highest temperature for chilling or cold storage | $2,770 | $5,000 |
$2,770
111,958
kWh
|
- | - | - | - | |
| 07 | 2.2621: Modify refrigeration system to operate at a lower pressure | $10,430 | $50,000 |
$9,805
395,662
kWh
|
$625
-
kW-mo/yr
|
- | - | - | |
| 08 | 3.5315: Lease / purchase baler; sell cardboard to recycler | $120 | - | - | - | - |
$120
-
lb
|
- | |
| TOTAL RECOMMENDED | $69,710 | $232,270 |
$52,905
2,134,818
kWh
|
$6,045
-
kW-mo/yr
|
$11,120
-
MMBtu
|
$120
-
lb
|
$(-480.0) | ||
| TOTAL IMPLEMENTED | $59,150 | $225,270 |
$42,345
1,708,382
kWh
|
$6,045
-
kW-mo/yr
|
$11,120
-
MMBtu
|
$120
-
lb
|
$(-480.0) | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs