| Assessment Year | 1996 |
|---|---|
| Principal Product | printed bags |
| NAICS |
n/a
|
| SIC | 2671: Packaging Paper and Plastics Film, Coated and Laminated |
| Sales Range | $10 M to 50M |
| # of Employees | 70 |
| Plant Area |
45,000
ft2
|
| Annual Production | 13,600,000
pieces
|
| Production Hrs. Annual | 2,250
hrs
|
| Location (State) | Oregon |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $14,289 | 265,240 |
kWh
|
$0.054 |
| Electricity Demand | $351 | 1,296 |
kW-mo/yr
|
$0.27 |
| Electricity Fees | $698 | - |
|
- |
| Natural Gas | $14,959 | 2,935 |
MMBtu
|
$5.10 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $3,894 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $3,354 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 3.5315: Lease / purchase baler; sell cardboard to recycler | $1,953 | - | - | - | - |
$1,953
-
lb
|
- | - | |
| 02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $217 | $500 |
$149
4,396
kWh
|
$68
-
kW-mo/yr
|
- | - | - | - | |
| 03 | 2.3212: Optimize plant power factor | $216 | $600 | - | - | $216 | - | - | - | |
| 04 | 2.4133: Use most efficient type of electric motors | $324 | $1,589 |
$232
7,034
kWh
|
$92
-
kW-mo/yr
|
- | - | - | - | |
| 05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,184 | $6,354 |
$654
19,637
kWh
|
$267
-
kW-mo/yr
|
- | - | $67 | $196 | |
| TOTAL RECOMMENDED | $3,894 | $9,043 |
$1,035
31,067
kWh
|
$427
-
kW-mo/yr
|
$216 |
$1,953
-
lb
|
$67 | $196 | ||
| TOTAL IMPLEMENTED | $3,354 | $6,854 |
$803
24,033
kWh
|
$335
-
kW-mo/yr
|
- |
$1,953
-
lb
|
$67 | $196 | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs