ITAC Assessment: OR0276
ITAC logo
ITAC Assessment: OR0276
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1996
Principal Product printed bags
NAICS
n/a
SIC 2671: Packaging Paper and Plastics Film, Coated and Laminated
Sales Range $10
M
to 50
M
# of Employees 70
Plant Area 45,000
ft2
Annual Production 13,600,000
pieces
Production Hrs. Annual 2,250
hrs
Location (State) Oregon

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $14,289 265,240
kWh
Electricity Demand $351 1,296
kW-mo/yr
Electricity Fees $698 -
Natural Gas $14,959 2,935
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $3,894 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $3,354

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Solid Waste (non-haz) Savings Personnel Changes Savings Ancillary Material Cost Savings
01 3.5315: Lease / purchase baler; sell cardboard to recycler $1,953 - - - - $1,953
-
lb
- -
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $217 $500 $149
4,396
kWh
$68
-
kW-mo/yr
- - - -
03 2.3212: Optimize plant power factor $216 $600 - - $216 - - -
04 2.4133: Use most efficient type of electric motors $324 $1,589 $232
7,034
kWh
$92
-
kW-mo/yr
- - - -
05 2.7142: Utilize higher efficiency lamps and/or ballasts $1,184 $6,354 $654
19,637
kWh
$267
-
kW-mo/yr
- - $67 $196
TOTAL RECOMMENDED $3,894 $9,043 $1,035
31,067
kWh
$427
-
kW-mo/yr
$216 $1,953
-
lb
$67 $196
TOTAL IMPLEMENTED $3,354 $6,854 $803
24,033
kWh
$335
-
kW-mo/yr
- $1,953
-
lb
$67 $196
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs