ITAC Assessment: OR0273
ITAC logo
ITAC Assessment: OR0273
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1996
Principal Product Zirconium and Titanium Rods
NAICS
n/a
SIC 3443: Fabricated Plate Work (Boiler Shops)
Sales Range $10
M
to 50
M
# of Employees 250
Plant Area 150,000
ft2
Annual Production 543,000
lb
Production Hrs. Annual 8,424
hrs
Location (State) Washington

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $211,934 9,203,400
kWh
Electricity Demand $107,040 20,388
kW-mo/yr
Electricity Fees $764 -
Natural Gas $146,803 33,095
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $59,179 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $2,347

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $10,150 $6,000 $7,550
341,735
kWh
$2,600
-
kW-mo/yr
- -
02 2.1231: Establish burner maintenance schedule for boilers $1,544 $1,000 - - $1,544
-
MMBtu
-
03 2.4133: Use most efficient type of electric motors $803 $1,775 $690
31,360
kWh
$113
-
kW-mo/yr
- -
04 2.4111: Utilize energy-efficient belts and other improved mechanisms $947 $5,575 $813
36,928
kWh
$134
-
kW-mo/yr
- -
05 3.3133: Use other waste concentration methods $45,735 $67,500 $(-1,110.0)
(-32,532)
kWh
$(-250.0)
-
kW-mo/yr
$(-23,122.0)
-
MMBtu
$70,217
-
lb
TOTAL RECOMMENDED $59,179 $81,850 $7,943
377,491
kWh
$2,597
-
kW-mo/yr
$(-21,578.0)
-
MMBtu
$70,217
-
lb
TOTAL IMPLEMENTED $2,347 $2,775 $690
31,360
kWh
$113
-
kW-mo/yr
$1,544
-
MMBtu
-
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs