| Assessment Year | 1996 |
|---|---|
| Principal Product | Zirconium and Titanium Rods |
| NAICS |
n/a
|
| SIC | 3443: Fabricated Plate Work (Boiler Shops) |
| Sales Range | $10 M to 50M |
| # of Employees | 250 |
| Plant Area |
150,000
ft2
|
| Annual Production | 543,000
lb
|
| Production Hrs. Annual | 8,424
hrs
|
| Location (State) | Washington |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $211,934 | 9,203,400 |
kWh
|
$0.023 |
| Electricity Demand | $107,040 | 20,388 |
kW-mo/yr
|
$5.25 |
| Electricity Fees | $764 | - |
|
- |
| Natural Gas | $146,803 | 33,095 |
MMBtu
|
$4.44 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $59,179 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $2,347 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $10,150 | $6,000 |
$7,550
341,735
kWh
|
$2,600
-
kW-mo/yr
|
- | - | |
| 02 | 2.1231: Establish burner maintenance schedule for boilers | $1,544 | $1,000 | - | - |
$1,544
-
MMBtu
|
- | |
| 03 | 2.4133: Use most efficient type of electric motors | $803 | $1,775 |
$690
31,360
kWh
|
$113
-
kW-mo/yr
|
- | - | |
| 04 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $947 | $5,575 |
$813
36,928
kWh
|
$134
-
kW-mo/yr
|
- | - | |
| 05 | 3.3133: Use other waste concentration methods | $45,735 | $67,500 |
$(-1,110.0)
(-32,532)
kWh
|
$(-250.0)
-
kW-mo/yr
|
$(-23,122.0)
-
MMBtu
|
$70,217
-
lb
|
|
| TOTAL RECOMMENDED | $59,179 | $81,850 |
$7,943
377,491
kWh
|
$2,597
-
kW-mo/yr
|
$(-21,578.0)
-
MMBtu
|
$70,217
-
lb
|
||
| TOTAL IMPLEMENTED | $2,347 | $2,775 |
$690
31,360
kWh
|
$113
-
kW-mo/yr
|
$1,544
-
MMBtu
|
- | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs