| Assessment Year | 1996 |
|---|---|
| Principal Product | fruit juice, concentrate, jelly |
| NAICS |
n/a
|
| SIC | 2037: Frozen Fruits, Fruit Juices, and Vegetables |
| Sales Range | $50 M to 100M |
| # of Employees | 160 |
| Plant Area |
212,000
ft2
|
| Annual Production | 14,000,000
Tgal
|
| Production Hrs. Annual | 2,040
hrs
|
| Location (State) | Washington |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $162,887 | 6,533,998 |
kWh
|
$0.025 |
| Electricity Demand | $90,264 | 15,504 |
kW-mo/yr
|
$5.82 |
| Electricity Fees | $5,328 | - |
|
- |
| Natural Gas | $137,368 | 54,947 |
MMBtu
|
$2.50 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $53,880 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $34,220 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Solid Waste (non-haz) Savings | Water Consumption Savings |
|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.2621: Modify refrigeration system to operate at a lower pressure | $9,100 | - |
$9,100
412,075
kWh
|
- | - | - | - | - | |
| 02 | 2.4239: Eliminate or reduce compressed air usage | $22,000 | $5,000 |
$17,000
771,102
kWh
|
$5,000
-
kW-mo/yr
|
- | - | - | - | |
| 03 | 2.1394: Replace steam jets on vacuum system with electric motor driven vacuum pumps | $10,070 | $6,000 |
$(-260.0)
(-11,723)
kWh
|
$(-380.0)
-
kW-mo/yr
|
$10,710
-
MMBtu
|
- | - | - | |
| 04 | 2.1232: Keep boiler tubes clean | $330 | $500 | - | - |
$330
-
MMBtu
|
- | - | - | |
| 05 | 2.4133: Use most efficient type of electric motors | $6,740 | $16,120 |
$4,170
188,746
kWh
|
$2,570
-
kW-mo/yr
|
- | - | - | - | |
| 06 | 3.5212: Regrind, reuse, or sell scrap plastic parts | $160 | - | - | - | - | - |
$160
-
lb
|
- | |
| 07 | 3.4157: Replace water cooling on processes with air cooling | $5,480 | $3,000 |
$(-640.0)
(-29,015)
kWh
|
$(-950.0)
-
kW-mo/yr
|
- |
$4,090
-
Tgal
|
- |
$2,980
-
Tgal
|
|
| TOTAL RECOMMENDED | $53,880 | $30,620 |
$29,370
1,331,185
kWh
|
$6,240
-
kW-mo/yr
|
$11,040
-
MMBtu
|
$4,090
-
Tgal
|
$160
-
lb
|
$2,980
-
Tgal
|
||
| TOTAL IMPLEMENTED | $34,220 | $24,120 |
$20,530
930,833
kWh
|
$6,620
-
kW-mo/yr
|
- |
$4,090
-
Tgal
|
- |
$2,980
-
Tgal
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Solid Waste (non-haz) Savings | Water Consumption Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs