ITAC Assessment: OR0271
ITAC logo
ITAC Assessment: OR0271
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1996
Principal Product fruit juice, concentrate, jelly
NAICS
n/a
SIC 2037: Frozen Fruits, Fruit Juices, and Vegetables
Sales Range $50
M
to 100
M
# of Employees 160
Plant Area 212,000
ft2
Annual Production 14,000,000
Tgal
Production Hrs. Annual 2,040
hrs
Location (State) Washington

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $162,887 6,533,998
kWh
Electricity Demand $90,264 15,504
kW-mo/yr
Electricity Fees $5,328 -
Natural Gas $137,368 54,947
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $53,880 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $34,220

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Solid Waste (non-haz) Savings Water Consumption Savings
01 2.2621: Modify refrigeration system to operate at a lower pressure $9,100 - $9,100
412,075
kWh
- - - - -
02 2.4239: Eliminate or reduce compressed air usage $22,000 $5,000 $17,000
771,102
kWh
$5,000
-
kW-mo/yr
- - - -
03 2.1394: Replace steam jets on vacuum system with electric motor driven vacuum pumps $10,070 $6,000 $(-260.0)
(-11,723)
kWh
$(-380.0)
-
kW-mo/yr
$10,710
-
MMBtu
- - -
04 2.1232: Keep boiler tubes clean $330 $500 - - $330
-
MMBtu
- - -
05 2.4133: Use most efficient type of electric motors $6,740 $16,120 $4,170
188,746
kWh
$2,570
-
kW-mo/yr
- - - -
06 3.5212: Regrind, reuse, or sell scrap plastic parts $160 - - - - - $160
-
lb
-
07 3.4157: Replace water cooling on processes with air cooling $5,480 $3,000 $(-640.0)
(-29,015)
kWh
$(-950.0)
-
kW-mo/yr
- $4,090
-
Tgal
- $2,980
-
Tgal
TOTAL RECOMMENDED $53,880 $30,620 $29,370
1,331,185
kWh
$6,240
-
kW-mo/yr
$11,040
-
MMBtu
$4,090
-
Tgal
$160
-
lb
$2,980
-
Tgal
TOTAL IMPLEMENTED $34,220 $24,120 $20,530
930,833
kWh
$6,620
-
kW-mo/yr
- $4,090
-
Tgal
- $2,980
-
Tgal
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Solid Waste (non-haz) Savings Water Consumption Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs