ITAC Assessment: OR0267
ITAC logo
ITAC Assessment: OR0267
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1996
Principal Product Electrical Enclosures
NAICS
n/a
SIC 3699: Electrical Machinery, Equipment, and Supplies, Not Elsewhere
Sales Range $5
M
to 10
M
# of Employees 85
Plant Area 44,000
ft2
Annual Production 30,000,000
pieces
Production Hrs. Annual 4,000
hrs
Location (State) Oregon

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $73,245 1,941,970
kWh
Electricity Demand $25,074 6,538
kW-mo/yr
Electricity Fees $691 -
Natural Gas $99,491 26,646
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $5,944 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $3,744

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Primary Raw Material Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $1,697 - $975
26,964
kWh
$465
-
kW-mo/yr
- $257
02 2.2511: Insulate bare equipment $2,200 $2,460 - - $2,200
-
MMBtu
-
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $700 $1,000 $500
14,068
kWh
$200
-
kW-mo/yr
- -
04 2.4133: Use most efficient type of electric motors $1,347 $3,008 $919
25,498
kWh
$428
-
kW-mo/yr
- -
TOTAL RECOMMENDED $5,944 $6,468 $2,394
66,530
kWh
$1,093
-
kW-mo/yr
$2,200
-
MMBtu
$257
TOTAL IMPLEMENTED $3,744 $4,008 $2,394
66,530
kWh
$1,093
-
kW-mo/yr
- $257
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs