Assessment Year | 1996 |
---|---|
Principal Product | Formed Sheet Metal |
NAICS |
n/a
|
SIC | 3442: Metal Doors, Sash, Frames, Molding, and Trim Manufacturing |
Sales Range | $10 M to 50M |
# of Employees | 170 |
Plant Area |
50,000
ft2
|
Annual Production | 1,500,000
pieces
|
Production Hrs. Annual | 7,200
hrs
|
Location (State) | Oregon |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $52,647 | 1,415,006 |
kWh
|
$0.037 |
Electricity Demand | $12,058 | 2,868 |
kW-mo/yr
|
$4.20 |
Electricity Fees | $576 | - |
|
- |
Natural Gas | $19,315 | 4,566 |
MMBtu
|
$4.23 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $25,844 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $4,943 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Personnel Changes Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.6125: Keep equipment clean | $2,162 | - | - | - |
$2,282
-
MMBtu
|
- | $(-120.0) | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,493 | $1,000 |
$1,222
33,705
kWh
|
$271
-
kW-mo/yr
|
- | - | - | |
03 | 2.4133: Use most efficient type of electric motors | $1,288 | $2,371 |
$1,012
28,136
kWh
|
$276
-
kW-mo/yr
|
- | - | - | |
04 | 3.6112: Use filter and drying oven to reduce sludge volume | $20,901 | $62,500 |
$(-91.0)
(-2,638)
kWh
|
- |
$(-500.0)
-
MMBtu
|
$19,532
-
Tgal
|
$1,960 | |
TOTAL RECOMMENDED | $25,844 | $65,871 |
$2,143
59,203
kWh
|
$547
-
kW-mo/yr
|
$1,782
-
MMBtu
|
$19,532
-
Tgal
|
$1,840 | ||
TOTAL IMPLEMENTED | $4,943 | $3,371 |
$2,234
61,841
kWh
|
$547
-
kW-mo/yr
|
$2,282
-
MMBtu
|
- | $(-120.0) |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs