| Assessment Year | 1996 |
|---|---|
| Principal Product | Pickles |
| NAICS |
n/a
|
| SIC | 2035: Pickled Fruits and Vegetables, Vegetable Sauces and Seasonings, and Salad Dressings |
| Sales Range | $10 M to 50M |
| # of Employees | 125 |
| Plant Area |
40,000
ft2
|
| Annual Production | 37,000,000
lb
|
| Production Hrs. Annual | 4,032
hrs
|
| Location (State) | Oregon |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $73,273 | 1,937,280 |
kWh
|
$0.038 |
| Electricity Demand | $18,626 | 4,968 |
kW-mo/yr
|
$3.75 |
| Electricity Fees | $5,746 | - |
|
- |
| Natural Gas | $91,943 | 36,663 |
MMBtu
|
$2.51 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $100,677 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $95,705 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.4231: Reduce the pressure of compressed air to the minimum required | $3,791 | $2,900 |
$4,119
114,009
kWh
|
$(-328.0)
-
kW-mo/yr
|
- | - | - | - | |
| 02 | 2.2123: Insulate feedwater tank | $1,450 | $2,383 | - | - | - |
$1,450
-
MMBtu
|
- | - | |
| 03 | 2.4234: Cool compressor air intake with heat exchanger | $1,824 | $4,012 |
$1,288
35,756
kWh
|
$536
-
kW-mo/yr
|
- | - | - | - | |
| 04 | 2.3212: Optimize plant power factor | $1,181 | $4,000 | - | - | $1,181 | - | - | - | |
| 05 | 3.3112: Utilize oxidation/reduction for neutralization | $92,431 | $120,000 |
$(-10,440.0)
(-289,273)
kWh
|
$(-1,900.0)
-
kW-mo/yr
|
- | - |
$117,121
-
lb
|
$(-12,350.0) | |
| TOTAL RECOMMENDED | $100,677 | $133,295 |
$(-5,033.0)
(-139,508)
kWh
|
$(-1,692.0)
-
kW-mo/yr
|
$1,181 |
$1,450
-
MMBtu
|
$117,121
-
lb
|
$(-12,350.0) | ||
| TOTAL IMPLEMENTED | $95,705 | $126,395 |
$(-9,152.0)
(-253,517)
kWh
|
$(-1,364.0)
-
kW-mo/yr
|
- |
$1,450
-
MMBtu
|
$117,121
-
lb
|
$(-12,350.0) | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs