Assessment Year | 1996 |
---|---|
Principal Product | Injection Molded Plastics |
NAICS |
n/a
|
SIC | 3089: Plastics Products, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 140 |
Plant Area |
60,000
ft2
|
Annual Production | 600,000
lb
|
Production Hrs. Annual | 6,000
hrs
|
Location (State) | Washington |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $74,910 | 2,515,240 |
kWh
|
$0.030 |
Electricity Demand | $11,531 | 7,188 |
kW-mo/yr
|
$1.60 |
Electricity Fees | $2,946 | - |
|
- |
Natural Gas | $5,919 | 1,122 |
MMBtu
|
$5.28 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $12,551 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $6,512 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 3.6192: Use a less expensive method of waste removal | $2,446 | $560 | - | - | - | - | $2,446 | |
02 | 2.2437: Recover waste heat from equipment | $1,920 | $1,190 | - | - | - |
$1,920
-
MMBtu
|
- | |
03 | 2.2511: Insulate bare equipment | $1,860 | $2,290 |
$1,860
62,720
kWh
|
- | - | - | - | |
04 | 2.4133: Use most efficient type of electric motors | $830 | $2,626 |
$730
24,619
kWh
|
$100
-
kW-mo/yr
|
- | - | - | |
05 | 2.3212: Optimize plant power factor | $2,259 | $6,400 | - | - | $2,259 | - | - | |
06 | 2.6231: Utilize controls to operate equipment only when needed | $2,660 | $16,440 |
$2,660
89,390
kWh
|
- | - | - | - | |
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $576 | $6,630 |
$518
17,292
kWh
|
$58
-
kW-mo/yr
|
- | - | - | |
TOTAL RECOMMENDED | $12,551 | $36,136 |
$5,768
194,021
kWh
|
$158
-
kW-mo/yr
|
$2,259 |
$1,920
-
MMBtu
|
$2,446 | ||
TOTAL IMPLEMENTED | $6,512 | $26,256 |
$3,908
131,301
kWh
|
$158
-
kW-mo/yr
|
- | - | $2,446 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs