| Assessment Year | 1995 |
|---|---|
| Principal Product | Printed Circuit Boards |
| NAICS |
n/a
|
| SIC | 3672: Printed Circuit Boards |
| Sales Range | $50 M to 100M |
| # of Employees | 300 |
| Plant Area |
91,000
ft2
|
| Annual Production | 3,000,000
pieces
|
| Production Hrs. Annual | 8,760
hrs
|
| Location (State) | Oregon |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $532,564 | 13,969,226 |
kWh
|
$0.038 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $95,720 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $53,054 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Primary Raw Material Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $1,668 | - |
$1,668
45,721
kWh
|
- | - | |
| 02 | 2.2437: Recover waste heat from equipment | $38,868 | $9,488 | - |
$38,868
-
MMBtu
|
- | |
| 03 | 2.2511: Insulate bare equipment | $407 | $227 | - |
$407
-
MMBtu
|
- | |
| 04 | 2.4133: Use most efficient type of electric motors | $949 | $1,180 |
$949
26,084
kWh
|
- | - | |
| 05 | 2.3212: Optimize plant power factor | $3,672 | $6,000 |
$3,672
-
kWh
|
- | - | |
| 06 | 2.4322: Use or replace with energy efficient substitutes | $1,402 | $6,389 |
$1,402
39,566
kWh
|
- | - | |
| 07 | 3.8132: Use less toxic and volatile solvent substitutes | $9,760 | - | - | - | $9,760 | |
| 08 | 3.1244: Reduce solution drag-out to prevent solution loss | $38,994 | $3,566 | - | - | $38,994 | |
| TOTAL RECOMMENDED | $95,720 | $26,850 |
$7,691
111,371
kWh
|
$39,275
-
MMBtu
|
$48,754 | ||
| TOTAL IMPLEMENTED | $53,054 | $17,284 |
$4,019
111,371
kWh
|
$39,275
-
MMBtu
|
$9,760 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Primary Raw Material Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs