| Assessment Year | 1994 |
|---|---|
| Principal Product | Cabinets |
| NAICS |
n/a
|
| SIC | 2434: Wood Kitchen Cabinets |
| Sales Range | $10 M to 50M |
| # of Employees | 240 |
| Plant Area |
250,000
ft2
|
| Annual Production | 136,000
pieces
|
| Production Hrs. Annual | 6,000
hrs
|
| Location (State) | Oregon |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $145,572 | 3,621,337 |
kWh
|
$0.040 |
| Natural Gas | $94,474 | 21,293 |
MMBtu
|
$4.44 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $47,092 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $45,728 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Solid Waste (non-haz) Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.2437: Recover waste heat from equipment | $1,968 | $5,768 | - |
$1,968
-
MMBtu
|
- | |
| 02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $4,407 | $4,000 |
$4,407
111,958
kWh
|
- | - | |
| 03 | 2.4133: Use most efficient type of electric motors | $558 | $1,345 |
$558
14,361
kWh
|
- | - | |
| 04 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $1,364 | $4,800 |
$1,364
34,584
kWh
|
- | - | |
| 05 | 2.3212: Optimize plant power factor | $695 | $2,000 |
$695
-
kWh
|
- | - | |
| 06 | 2.5125: Size air handling grills/ duct/s coils to minimize air resistance | $23,850 | $106,600 |
$13,310
338,511
kWh
|
$10,540
-
MMBtu
|
- | |
| 07 | 3.1192: Reduce scrap production | $14,250 | $6,500 | - | - |
$14,250
-
lb
|
|
| TOTAL RECOMMENDED | $47,092 | $131,013 |
$20,334
499,414
kWh
|
$12,508
-
MMBtu
|
$14,250
-
lb
|
||
| TOTAL IMPLEMENTED | $45,728 | $126,213 |
$18,970
464,830
kWh
|
$12,508
-
MMBtu
|
$14,250
-
lb
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs