ITAC Assessment: OR0212
ITAC logo
ITAC Assessment: OR0212
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1994
Principal Product lead acid batteries
NAICS
n/a
SIC 3691: Storage Batteries
Sales Range $10
M
to 50
M
# of Employees 280
Plant Area 198,000
ft2
Annual Production 195
pieces
Production Hrs. Annual 5,928
hrs
Location (State) Oregon

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $689,273 20,565,065
kWh
Natural Gas $248,791 60,759
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $293,573 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $224,117

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Solid Waste (non-haz) Savings Administrative Changes Savings
01 2.7111: Reduce illumination to minimum necessary levels $4,043 - $4,043
123,974
kWh
- -
02 2.4133: Use most efficient type of electric motors $1,121 $1,763 $1,121
33,411
kWh
- -
03 2.4111: Utilize energy-efficient belts and other improved mechanisms $3,007 $12,425 $3,007
88,511
kWh
- -
04 2.8113: Purchase gas directly from a contract gas supplier $69,996 $30,000 - - $69,996
05 2.8114: Change rate schedules or other changes in utility service $51,397 - - - $51,397
06 2.3212: Optimize plant power factor $11,009 $45,344 $11,009
-
kWh
- -
07 3.5314: Use in-process recycling whenever possible $153,000 $106,000 - $153,000
-
lb
-
TOTAL RECOMMENDED $293,573 $195,532 $19,180
245,896
kWh
$153,000
-
lb
$121,393
TOTAL IMPLEMENTED $224,117 $137,763 $1,121
33,411
kWh
$153,000
-
lb
$69,996
Yearly Savings* Imp'd Cost* Electricity Usage Savings Solid Waste (non-haz) Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs