| Assessment Year | 1994 |
|---|---|
| Principal Product | lead acid batteries |
| NAICS |
n/a
|
| SIC | 3691: Storage Batteries |
| Sales Range | $10 M to 50M |
| # of Employees | 280 |
| Plant Area |
198,000
ft2
|
| Annual Production | 195
pieces
|
| Production Hrs. Annual | 5,928
hrs
|
| Location (State) | Oregon |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $689,273 | 20,565,065 |
kWh
|
$0.034 |
| Natural Gas | $248,791 | 60,759 |
MMBtu
|
$4.09 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $293,573 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $224,117 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.7111: Reduce illumination to minimum necessary levels | $4,043 | - |
$4,043
123,974
kWh
|
- | - | |
| 02 | 2.4133: Use most efficient type of electric motors | $1,121 | $1,763 |
$1,121
33,411
kWh
|
- | - | |
| 03 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $3,007 | $12,425 |
$3,007
88,511
kWh
|
- | - | |
| 04 | 2.8113: Purchase gas directly from a contract gas supplier | $69,996 | $30,000 | - | - | $69,996 | |
| 05 | 2.8114: Change rate schedules or other changes in utility service | $51,397 | - | - | - | $51,397 | |
| 06 | 2.3212: Optimize plant power factor | $11,009 | $45,344 |
$11,009
-
kWh
|
- | - | |
| 07 | 3.5314: Use in-process recycling whenever possible | $153,000 | $106,000 | - |
$153,000
-
lb
|
- | |
| TOTAL RECOMMENDED | $293,573 | $195,532 |
$19,180
245,896
kWh
|
$153,000
-
lb
|
$121,393 | ||
| TOTAL IMPLEMENTED | $224,117 | $137,763 |
$1,121
33,411
kWh
|
$153,000
-
lb
|
$69,996 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs