ITAC Assessment: OR0207
ITAC logo
ITAC Assessment: OR0207
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1994
Principal Product Bar Code Scanners
NAICS
n/a
SIC 3577: Computer Peripheral Equipment, Not Elsewhere Classified
Sales Range $50
M
to 100
M
# of Employees 470
Plant Area
n/a
Annual Production 0
units
Production Hrs. Annual 5,304
hrs
Location (State) Oregon

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $121,464 3,845,252
kWh
Natural Gas $4,548 780
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $8,447 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $5,596

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings
01 2.6218: Turn off equipment when not in use $2,165 - $2,165
111,665
kWh
02 2.3212: Optimize plant power factor $686 $900 $686
-
kWh
03 2.4133: Use most efficient type of electric motors $258 $514 $258
7,327
kWh
04 2.7142: Utilize higher efficiency lamps and/or ballasts $5,338 $17,685 $5,338
183,470
kWh
TOTAL RECOMMENDED $8,447 $19,099 $8,447
302,462
kWh
TOTAL IMPLEMENTED $5,596 $18,199 $5,596
190,797
kWh
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs