Assessment Year | 1994 |
---|---|
Principal Product | Barges |
NAICS |
n/a
|
SIC | 3731: Ship Building and Repairing |
Sales Range | $10 M to 50M |
# of Employees | 80 |
Plant Area |
n/a
|
Annual Production | 3
pieces
|
Production Hrs. Annual | 4,500
hrs
|
Location (State) | Oregon |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $117,058 | 2,278,722 |
kWh
|
$0.051 |
Natural Gas | $4,213 | 830 |
MMBtu
|
$5.08 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $21,987 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $18,597 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Personnel Changes Savings |
---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,028 | $2,000 |
$1,028
21,981
kWh
|
- | |
02 | 2.4239: Eliminate or reduce compressed air usage | $1,951 | $1,800 |
$1,951
36,928
kWh
|
- | |
03 | 2.4131: Size electric motors for peak operating efficiency | $13,766 | $17,137 |
$13,766
293,669
kWh
|
- | |
04 | 2.7124: Make a practice of turning off lights when not needed | $310 | $341 |
$225
4,982
kWh
|
$85 | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $560 | $1,302 |
$350
9,379
kWh
|
$210 | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $869 | $2,738 |
$921
17,878
kWh
|
$(-52.0) | |
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $703 | $3,150 |
$796
13,775
kWh
|
$(-93.0) | |
08 | 2.4133: Use most efficient type of electric motors | $456 | $50 |
$456
9,965
kWh
|
- | |
09 | 2.3137: Use power during off-peak periods | $1,817 | - |
$1,817
-
kWh
|
- | |
10 | 2.3212: Optimize plant power factor | $527 | $1,350 |
$527
-
kWh
|
- | |
TOTAL RECOMMENDED | $21,987 | $29,868 |
$21,837
408,557
kWh
|
$150 | ||
TOTAL IMPLEMENTED | $18,597 | $25,075 |
$18,649
380,421
kWh
|
$(-52.0) | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Personnel Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs