ITAC Assessment: OR0196
ITAC logo
ITAC Assessment: OR0196
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1994
Principal Product Barges
NAICS
n/a
SIC 3731: Ship Building and Repairing
Sales Range $10
M
to 50
M
# of Employees 80
Plant Area
n/a
Annual Production 3
pieces
Production Hrs. Annual 4,500
hrs
Location (State) Oregon

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $117,058 2,278,722
kWh
Natural Gas $4,213 830
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $21,987 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $18,597

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Personnel Changes Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,028 $2,000 $1,028
21,981
kWh
-
02 2.4239: Eliminate or reduce compressed air usage $1,951 $1,800 $1,951
36,928
kWh
-
03 2.4131: Size electric motors for peak operating efficiency $13,766 $17,137 $13,766
293,669
kWh
-
04 2.7124: Make a practice of turning off lights when not needed $310 $341 $225
4,982
kWh
$85
05 2.7142: Utilize higher efficiency lamps and/or ballasts $560 $1,302 $350
9,379
kWh
$210
06 2.7142: Utilize higher efficiency lamps and/or ballasts $869 $2,738 $921
17,878
kWh
$(-52.0)
07 2.7142: Utilize higher efficiency lamps and/or ballasts $703 $3,150 $796
13,775
kWh
$(-93.0)
08 2.4133: Use most efficient type of electric motors $456 $50 $456
9,965
kWh
-
09 2.3137: Use power during off-peak periods $1,817 - $1,817
-
kWh
-
10 2.3212: Optimize plant power factor $527 $1,350 $527
-
kWh
-
TOTAL RECOMMENDED $21,987 $29,868 $21,837
408,557
kWh
$150
TOTAL IMPLEMENTED $18,597 $25,075 $18,649
380,421
kWh
$(-52.0)
Yearly Savings* Imp'd Cost* Electricity Usage Savings Personnel Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs