ITAC Assessment: OR0195
ITAC logo
ITAC Assessment: OR0195
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1993
Principal Product PVC pipe
NAICS
n/a
SIC 3084: Plastics Pipe
Sales Range $10
M
to 50
M
# of Employees 55
Plant Area 40,000
ft2
Annual Production 50,000,000
lb
Production Hrs. Annual 8,736
hrs
Location (State) Oregon

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $274,353 10,527,550
kWh
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $17,929 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $16,650

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings
01 2.4111: Utilize energy-efficient belts and other improved mechanisms $154 - $154
5,569
kWh
02 2.4133: Use most efficient type of electric motors $1,031 $2,722 $1,031
38,101
kWh
03 2.4111: Utilize energy-efficient belts and other improved mechanisms $1,279 $6,675 $1,279
47,186
kWh
04 2.6218: Turn off equipment when not in use $5,474 - $5,474
272,274
kWh
05 2.2511: Insulate bare equipment $9,991 $10,187 $9,991
392,732
kWh
TOTAL RECOMMENDED $17,929 $19,584 $17,929
755,862
kWh
TOTAL IMPLEMENTED $16,650 $12,909 $16,650
708,676
kWh
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs