Assessment Year | 1993 |
---|---|
Principal Product | Dimensional Lumber |
NAICS |
n/a
|
SIC | 2421: Sawmills and Planing Mills, General |
Sales Range | $50 M to 100M |
# of Employees | 110 |
Plant Area |
n/a
|
Annual Production | 67,000
thousand feet
|
Production Hrs. Annual | 8,736
hrs
|
Location (State) | Oregon |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $526,062 | 12,853,459 |
kWh
|
$0.041 |
Natural Gas | $375,672 | 101,883 |
MMBtu
|
$3.69 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $155,672 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $48,735 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Personnel Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.4231: Reduce the pressure of compressed air to the minimum required | $10,305 | $1,800 |
$10,305
314,478
kWh
|
- | - | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $5,623 | $5,500 |
$5,623
146,249
kWh
|
- | - | |
03 | 2.3412: Use waste heat to produce steam to drive a steam turbine-generator | $75,830 | $146,156 |
$51,348
1,566,530
kWh
|
$24,482
-
MMBtu
|
- | |
04 | 2.2511: Insulate bare equipment | $1,468 | $1,287 | - |
$1,468
-
MMBtu
|
- | |
05 | 2.4131: Size electric motors for peak operating efficiency | $29,864 | $32,720 |
$29,864
910,903
kWh
|
- | - | |
06 | 2.7134: Use photocell controls | $12,486 | $4,100 |
$10,279
251,172
kWh
|
- | $2,207 | |
07 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $2,372 | - |
$2,372
54,220
kWh
|
- | - | |
08 | 2.4133: Use most efficient type of electric motors | $1,243 | $3,171 |
$1,243
31,653
kWh
|
- | - | |
09 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $2,921 | $9,700 |
$2,921
75,615
kWh
|
- | - | |
10 | 2.3212: Optimize plant power factor | $13,560 | $28,500 |
$13,560
-
kWh
|
- | - | |
TOTAL RECOMMENDED | $155,672 | $232,934 |
$127,515
3,350,820
kWh
|
$25,950
-
MMBtu
|
$2,207 | ||
TOTAL IMPLEMENTED | $48,735 | $50,887 |
$45,060
841,734
kWh
|
$1,468
-
MMBtu
|
$2,207 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Personnel Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs