ITAC Assessment: MA0824
ITAC logo
ITAC Assessment: MA0824
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2021
Principal Product Electrical Surface Mount Raceways
NAICS 335931: Current-Carrying Wiring Device Manufacturing
SIC 3643: Current-Carrying Wiring Devices
Sales Range $100
M
to 500
M
# of Employees 250
Plant Area 260,000
ft2
Annual Production 20,400,000
lb
Production Hrs. Annual 4,250
hrs
Location (State) Connecticut

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $102,489 1,081,693
kWh
Electricity Demand $147,358 9,689
kW-mo/yr
Electricity Fees $10,255 -
Natural Gas $365,183 59,457
MMBtu
Waste Disposal Costs
Water Usage $30,777 2,519
Tgal
TOTAL YEARLY COSTS $656,062
RECOMMENDED SAVINGS* $36,164 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $9,786

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.1224: Replace boiler $15,999 $29,000 - - $15,999
-
MMBtu
02 2.9114: Use solar heat to make electricty $10,379 $54,695 $4,082
42,964
kWh
$6,297
-
kW-mo/yr
-
03 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $6,177 $29,750 $6,177
65,025
kWh
- -
04 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $2,118 $7,710 $2,118
22,292
kWh
- -
05 2.1121: Use insulation in furnaces to facilitate heating / cooling $1,491 $6,300 - - $1,491
-
MMBtu
TOTAL RECOMMENDED $36,164 $127,455 $12,377
130,281
kWh
$6,297
-
kW-mo/yr
$17,490
-
MMBtu
TOTAL IMPLEMENTED $9,786 $43,760 $8,295
87,317
kWh
- $1,491
-
MMBtu
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs