| Assessment Year | 2021 |
|---|---|
| Principal Product | Electrical Surface Mount Raceways |
| NAICS | 335931: Current-Carrying Wiring Device Manufacturing |
| SIC | 3643: Current-Carrying Wiring Devices |
| Sales Range | $100 M to 500M |
| # of Employees | 250 |
| Plant Area |
260,000
ft2
|
| Annual Production | 20,400,000
lb
|
| Production Hrs. Annual | 4,250
hrs
|
| Location (State) | Connecticut |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $102,489 | 1,081,693 |
kWh
|
$0.095 | |
| Electricity Demand | $147,358 | 9,689 |
kW-mo/yr
|
$15.21 | |
| Electricity Fees | $10,255 | - |
|
- | |
| Natural Gas | $365,183 | 59,457 |
MMBtu
|
$6.14 | |
| Waste Disposal Costs | |||||
| Water Usage | $30,777 | 2,519 |
Tgal
|
$12.22 | |
| TOTAL YEARLY COSTS | $656,062 | ||||
| RECOMMENDED SAVINGS* | $36,164 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | $9,786 | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.1224: Replace boiler | $15,999 | $29,000 | - | - |
$15,999
-
MMBtu
|
|
| 02 | 2.9114: Use solar heat to make electricty | $10,379 | $54,695 |
$4,082
42,964
kWh
|
$6,297
-
kW-mo/yr
|
- | |
| 03 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $6,177 | $29,750 |
$6,177
65,025
kWh
|
- | - | |
| 04 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $2,118 | $7,710 |
$2,118
22,292
kWh
|
- | - | |
| 05 | 2.1121: Use insulation in furnaces to facilitate heating / cooling | $1,491 | $6,300 | - | - |
$1,491
-
MMBtu
|
|
| TOTAL RECOMMENDED | $36,164 | $127,455 |
$12,377
130,281
kWh
|
$6,297
-
kW-mo/yr
|
$17,490
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $9,786 | $43,760 |
$8,295
87,317
kWh
|
- |
$1,491
-
MMBtu
|
||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs