| Assessment Year | 1993 |
|---|---|
| Principal Product | Alder Veneer |
| NAICS |
n/a
|
| SIC | 2435: Hardwood Veneer and Plywood |
| Sales Range | $1 M to 5M |
| # of Employees | 60 |
| Plant Area |
n/a
|
| Annual Production | 780,256
thousand feet
|
| Production Hrs. Annual | 6,640
hrs
|
| Location (State) | Oregon |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $103,201 | 2,037,808 |
kWh
|
$0.051 |
| Natural Gas | $92,332 | 25,119 |
MMBtu
|
$3.68 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $15,590 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $10,226 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Personnel Changes Savings |
|---|---|---|---|---|---|---|
| 01 | 2.4239: Eliminate or reduce compressed air usage | $1,194 | $640 |
$1,194
23,447
kWh
|
- | |
| 02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,086 | $1,500 |
$1,086
23,740
kWh
|
- | |
| 03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $5,364 | $9,300 |
$5,364
136,284
kWh
|
- | |
| 04 | 2.7124: Make a practice of turning off lights when not needed | $604 | - |
$527
13,482
kWh
|
$77 | |
| 05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,419 | $1,107 |
$1,220
28,136
kWh
|
$199 | |
| 06 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $498 | - |
$498
9,965
kWh
|
- | |
| 07 | 2.4133: Use most efficient type of electric motors | $422 | $1,567 |
$422
8,792
kWh
|
- | |
| 08 | 2.4133: Use most efficient type of electric motors | $4,565 | $21,540 |
$4,565
83,529
kWh
|
- | |
| 09 | 2.3212: Optimize plant power factor | $438 | $1,125 |
$438
-
kWh
|
- | |
| TOTAL RECOMMENDED | $15,590 | $36,779 |
$15,314
327,375
kWh
|
$276 | ||
| TOTAL IMPLEMENTED | $10,226 | $27,479 |
$9,950
191,091
kWh
|
$276 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Personnel Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs