ITAC Assessment: OR0170
ITAC logo
ITAC Assessment: OR0170
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1993
Principal Product Circuit Boards
NAICS
n/a
SIC 3672: Printed Circuit Boards
Sales Range $50
M
to 100
M
# of Employees 556
Plant Area 3,000
ft2
Annual Production 428
thousand feet
Production Hrs. Annual 8,736
hrs
Location (State) Oregon

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $468,032 18,121,044
kWh
Natural Gas $125,378 34,159
MMBtu
Other Energy $40,494 -
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $30,943 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $23,567

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings LPG Savings Administrative Changes Savings
01 2.7124: Make a practice of turning off lights when not needed $10,430 $750 $7,220
338,218
kWh
- $3,210
02 2.7142: Utilize higher efficiency lamps and/or ballasts $831 $2,940 $960
36,049
kWh
- $(-129.0)
03 2.6218: Turn off equipment when not in use $3,875 - $3,875
215,416
kWh
- -
04 2.1232: Keep boiler tubes clean $1,644 $1,000 - $1,644
-
MMBtu
-
05 2.3212: Optimize plant power factor $6,396 $6,750 $6,396
-
kWh
- -
06 3.4115: Recover and reuse cooling water $5,728 $20,750 $5,728
314,771
kWh
- -
07 2.4133: Use most efficient type of electric motors $391 $1,519 $391
14,361
kWh
- -
08 2.4111: Utilize energy-efficient belts and other improved mechanisms $1,648 $6,800 $1,648
62,134
kWh
- -
TOTAL RECOMMENDED $30,943 $40,509 $26,218
980,949
kWh
$1,644
-
MMBtu
$3,081
TOTAL IMPLEMENTED $23,567 $12,959 $18,842
604,044
kWh
$1,644
-
MMBtu
$3,081
Yearly Savings* Imp'd Cost* Electricity Usage Savings LPG Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs