ITAC Assessment: OR0148
ITAC logo
ITAC Assessment: OR0148
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1992
Principal Product CUSTOM MOLDED PLASTICS
NAICS
n/a
SIC 3089: Plastics Products, Not Elsewhere Classified
Sales Range $1
M
to 5
M
# of Employees 21
Plant Area
n/a
Annual Production 214,000
lb
Production Hrs. Annual 4,080
hrs
Location (State) Oregon

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $53,489 620,457
kWh
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $9,279 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $6,993

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings
01 2.6212: Turn off equipment during breaks, reduce operating time $942 - $942
19,050
kWh
02 2.4111: Utilize energy-efficient belts and other improved mechanisms $86 - $86
879
kWh
03 3.4151: Minimize water usage $1,770 $574 $1,770
28,429
kWh
04 2.3191: Use demand controller or load shedder $4,487 $2,700 $4,487
-
kWh
05 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $934 $1,000 $934
14,947
kWh
06 2.2511: Insulate bare equipment $516 $1,090 $516
6,155
kWh
07 2.4133: Use most efficient type of electric motors $544 $228 $544
6,448
kWh
TOTAL RECOMMENDED $9,279 $5,592 $9,279
75,908
kWh
TOTAL IMPLEMENTED $6,993 $3,928 $6,993
41,324
kWh
Yearly Savings* Imp'd Cost* Electricity Usage Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs