ITAC Assessment: OR0138
ITAC logo
ITAC Assessment: OR0138
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1992
Principal Product PLYWOOD
NAICS
n/a
SIC 2436: Softwood Veneer and Plywood
Sales Range $10
M
to 50
M
# of Employees 150
Plant Area
n/a
Annual Production 138,800
thousand feet
Production Hrs. Annual 8,736
hrs
Location (State) Oregon

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $1,047,819 26,935,815
kWh
Natural Gas $59,914 14,677
MMBtu
Wood $414,000 364,320
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $39,038 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $19,339

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Wood Savings Administrative Changes Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $785 - $889
24,619
kWh
- - $(-104.0)
02 2.7111: Reduce illumination to minimum necessary levels $3,014 - $2,492
62,134
kWh
- - $522
03 2.2122: Install / repair insulation on condensate lines $500 $651 - $109
-
MMBtu
$391
-
MMBtu
-
04 2.7142: Utilize higher efficiency lamps and/or ballasts $15,386 - $10,927
308,030
kWh
- - $4,459
05 2.3212: Optimize plant power factor $16,934 $36,000 $16,934
-
kWh
- - -
06 2.4133: Use most efficient type of electric motors $1,905 $4,384 $1,905
48,066
kWh
- - -
07 2.4111: Utilize energy-efficient belts and other improved mechanisms $514 $1,900 $514
10,551
kWh
- - -
TOTAL RECOMMENDED $39,038 $42,935 $33,661
453,400
kWh
$109
-
MMBtu
$391
-
MMBtu
$4,877
TOTAL IMPLEMENTED $19,339 $41,035 $18,839
48,066
kWh
$109
-
MMBtu
$391
-
MMBtu
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Wood Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs