Assessment Year | 1991 |
---|---|
Principal Product | BEEF AND PORK PRODUCTS |
NAICS |
n/a
|
SIC | 2011: Meat Packing Plants |
Sales Range | $10 M to 50M |
# of Employees | 85 |
Plant Area |
n/a
|
Annual Production | 20,000,000
lb
|
Production Hrs. Annual | 8,736
hrs
|
Location (State) | Oregon |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $97,777 | 2,307,444 |
kWh
|
$0.042 |
Natural Gas | $61,978 | 16,037 |
MMBtu
|
$3.86 |
LPG | $4,935 | 645 |
MMBtu
|
$7.65 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $10,249 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $10,249 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.6232: Install set-back timers | $1,778 | $225 |
$1,778
35,756
kWh
|
- | - | |
02 | 3.4154: Eliminate leaks in water lines and valves | $261 | - | - |
$208
-
MMBtu
|
$53 | |
03 | 2.2122: Install / repair insulation on condensate lines | $450 | $800 | - |
$450
-
MMBtu
|
- | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,399 | $4,936 |
$2,399
57,444
kWh
|
- | - | |
05 | 2.3212: Optimize plant power factor | $1,647 | $3,450 |
$1,647
-
kWh
|
- | - | |
06 | 2.4133: Use most efficient type of electric motors | $75 | $157 |
$75
1,758
kWh
|
- | - | |
07 | 2.2414: Use waste heat from hot flue gases to preheat | $3,347 | $3,453 | - |
$3,347
-
MMBtu
|
- | |
08 | 2.2122: Install / repair insulation on condensate lines | $292 | $881 | - |
$292
-
MMBtu
|
- | |
TOTAL RECOMMENDED | $10,249 | $13,902 |
$5,899
94,958
kWh
|
$4,297
-
MMBtu
|
$53 | ||
TOTAL IMPLEMENTED | $10,249 | $13,902 |
$5,899
94,958
kWh
|
$4,297
-
MMBtu
|
$53 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs