ITAC Assessment: OR0129
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1991
Principal Product DIMENSIONAL LUMBER
NAICS
n/a
SIC 2421: Sawmills and Planing Mills, General
Sales Range $10
M
to 50
M
# of Employees 125
Plant Area
n/a
Annual Production 70,000
thousand feet
Production Hrs. Annual 8,736
hrs
Location (State) Oregon

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $387,248 9,431,126
kWh
Wood $330,572 483,630
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $103,284 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $103,284

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Wood Savings Administrative Changes Savings
01 2.4111: Utilize energy-efficient belts and other improved mechanisms $1,102 - $1,102
23,154
kWh
- -
02 2.3131: Reschedule plant operations or reduce load to avoid peaks $4,277 - $10,517
-
kWh
- $(-6,240.0)
03 2.1233: Analyze flue gas for proper air/fuel ratio $19,236 $30,000 - $19,236
-
MMBtu
-
04 2.7111: Reduce illumination to minimum necessary levels $1,626 - $1,381
33,705
kWh
- $245
05 2.2441: Preheat boiler makeup water with waste process heat $3,068 $3,066 - $3,068
-
MMBtu
-
06 2.7142: Utilize higher efficiency lamps and/or ballasts $1,072 - $1,232
31,946
kWh
- $(-160.0)
07 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $31,573 $40,000 $31,573
779,895
kWh
- -
08 2.1131: Repair faulty insulation in furnaces, boilers, etc $522 $864 - $522
-
MMBtu
-
09 2.2122: Install / repair insulation on condensate lines $790 $1,430 - $790
-
MMBtu
-
10 2.7142: Utilize higher efficiency lamps and/or ballasts $2,172 - $1,615
43,669
kWh
- $557
11 2.3212: Optimize plant power factor $12,146 $26,250 $12,146
-
kWh
- -
12 2.4133: Use most efficient type of electric motors $952 $2,150 $952
22,567
kWh
- -
13 2.4111: Utilize energy-efficient belts and other improved mechanisms $3,521 $15,000 $3,521
87,046
kWh
- -
14 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $21,227 $64,975 $21,227
647,421
kWh
- -
TOTAL RECOMMENDED $103,284 $183,735 $85,266
1,669,403
kWh
$23,616
-
MMBtu
$(-5,598.0)
TOTAL IMPLEMENTED $103,284 $183,735 $85,266
1,669,403
kWh
$23,616
-
MMBtu
$(-5,598.0)
Yearly Savings* Imp'd Cost* Electricity Usage Savings Wood Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs